Recycle of waste streams
First Claim
1. In a process for producing delayed petroleum coke, wherein a liquid hydrocarbon feed stream is introduced into a delayed coking vessel under delayed coking conditions and the coke produced is quenched, the improvement comprising:
- treating a waste stream containing water, organic compounds and solids so as to cause attrition of said solids to produce a delayed coker quench stream containing from about 5 to about 35% by weight solids, water and less than about 6% by weight mobile organics, said solids in said coker quench stream having a particle size distribution such that greater than about 70% of the total solids volume comprises solids having a particle size of less than about 15 microns; and
introducing said coker quench stream into said coking vessel during quenching.
2 Assignments
0 Petitions
Accused Products
Abstract
A process for producing a delayed coker quench stream for use in the quench cycle of a delayed coking process wherein a waste stream containing water, organic compounds and solids is treated to produce a coker feed stream containing from about 5 to about 35% by weight solids, water and less than about 6% by weight mobile organics, the solids having a particle size distribution such that greater than about 70% of the total solids volume comprises solids having a particle size of less than about 15 microns.
-
Citations
10 Claims
-
1. In a process for producing delayed petroleum coke, wherein a liquid hydrocarbon feed stream is introduced into a delayed coking vessel under delayed coking conditions and the coke produced is quenched, the improvement comprising:
-
treating a waste stream containing water, organic compounds and solids so as to cause attrition of said solids to produce a delayed coker quench stream containing from about 5 to about 35% by weight solids, water and less than about 6% by weight mobile organics, said solids in said coker quench stream having a particle size distribution such that greater than about 70% of the total solids volume comprises solids having a particle size of less than about 15 microns; and introducing said coker quench stream into said coking vessel during quenching. - View Dependent Claims (2, 3, 4, 5)
-
-
6. A process for producing a delayed coker quench stream for use in producing delayed petroleum coke wherein a liquid hydrocarbon feed stream is introduced into a delayed coking vessel under delayed coking conditions and the coke produced is quenched comprising:
treating a waste stream containing water, organic compounds and solids so as to cause attrition of said solids to produce said delayed coker quench stream containing from about 5 to about 35% by weight solids, water and less than about 6% by weight mobile organics, said solids in said coker quench stream having a particle size distribution such that greater than about 70% of the total solids volume comprises solids having a particle size of less than about 15 microns. - View Dependent Claims (7, 8, 9, 10)
Specification