Scheduling method and system
First Claim
Patent Images
1. An apparatus for scheduling a combination of workers, tasks, and work centers, comprising:
- means for storing schedule and task information, delayed delivery costs, and inventory carrying costs;
means for generating an initial schedule based on the schedule and task information whereby workers are assigned to perform tasks at work centers; and
means for modifying the initial schedule based on the delayed delivery costs and inventory carrying costs whereby the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of other tasks.
0 Assignments
0 Petitions
Accused Products
Abstract
This invention provides a method and system for cost-based resource scheduling. This invention develops an initial resource schedule. This schedule is then represented as a Schedule Precedence Graph, which is an acyclic directed graph consisting of nodes and arcs. Each node corresponds to a task to be performed, and each arc corresponds to a technological or assigned task precedence. Each node is assigned a cost, which corresponds to cost or savings due to delaying the task one time unit. In this invention, the Maximum Flow Procedure is iteratively invoked to determine which tasks can be profitably delayed.
153 Citations
19 Claims
-
1. An apparatus for scheduling a combination of workers, tasks, and work centers, comprising:
-
means for storing schedule and task information, delayed delivery costs, and inventory carrying costs; means for generating an initial schedule based on the schedule and task information whereby workers are assigned to perform tasks at work centers; and means for modifying the initial schedule based on the delayed delivery costs and inventory carrying costs whereby the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of other tasks.
-
-
2. A method for reallocating a combination of workers, tasks, and work centers based on an initial allocation schedule, each task having an associated start time and an associated inventory carrying cost, each end-product task having an associated delayed delivery cost whereby the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of other tasks, the method comprising the steps of:
-
developing a Technological Precedence Graph based on product design, whereby the Technological Precedence Graph includes a plurality of nodes representing tasks and directed arcs connecting the nodes and defining technological precedence; developing a Schedule Precedence Graph based on the initial allocation schedule and Technological Precedence Graph additionally including arcs defining nonredundant schedule precedence; assigning each node in the Schedule Precedence Graph a supply value representing the cost of carrying inventory and delaying delivery; adding a fictitious node to the Schedule Precedence Graph for each end-product task scheduled for early delivery; assigning to each arc an initial capacity of zero in the arc direction and an infinite capacity in the direction opposite the arc; initializing a Facility Queue to contain nodes based on the Schedule Precedence Graph; selecting and removing the top node from the Facility Queue; determining whether the selected node has been on a Candidate List; generating the Candidate List of nodes based on the Schedule Precedence Graph and the selected node; generating a Move List and a Stay List of nodes based upon the Candidate List; revising the cumulative delay of the nodes in the Move List; recording the start times of the nodes in the Stay List; and reallocating the combination of workers, tasks, and work centers in accordance with the start time of the tasks and performing the tasks in accordance with the reallocation. - View Dependent Claims (3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)
-
-
14. A resource allocation system for controlling the allocation of workers, work centers, and tasks in a manufactory, the system comprising:
-
a memory; a plurality of input-output devices connected to the memory wherein data is transferred from the memory to the devices and from the devices to the memory; input means for controlling the retrieving of schedule data including worker, work center, and task data from an input-output device and the storing of the schedule data in the memory; first processing means for generating initial schedule data based on the schedule data stored in the memory wherein workers are assigned to work centers and tasks and for storing the initial schedule data in the memory; second processing means for generating modified schedule data based on the initial schedule data stored in the memory wherein the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to the delaying of the start of other tasks and for storing the modified schedule data in the memory; and output means for transferring the modified schedule data from the memory to an input-output device to effect the allocation of the resources.
-
-
15. An apparatus for controlling the performing of tasks by workers at work centers in a manufactory, comprising;
-
a central processing unit; a memory unit for storing data sent from the central processing unit and sending stored data to the central processing unit; data input means for receiving data relating to each task including delayed delivery costs and inventory carrying costs, data relating to each work center, and data relating to each worker; data storage means for storing the task, work center, and worker data received from the data input means in the memory unit; first data processing means, working cooperatively with the central processing unit and the memory unit, for generating initial schedule data based on the task, work center, and worker data stored in the memory unit and for storing the initial schedule data in the memory unit; second data processing means, working cooperatively with the central processing unit and the memory unit, for generating final schedule data based on the initial schedule data stored in the memory unit and for storing the final schedule data in the memory unit; and data output means for retrieving the final schedule data from the memory unit and for outputting the final schedule data to effect the controlling of the performing of the tasks by the workers at the work centers.
-
-
16. A computer system for controlling the allocation of workers, tasks, and work centers in a manufactory, the system comprising:
-
a computer having a central processing unit, a memory, and input-output devices; inputting means for inputting schedule and task data, including delayed delivery costs and inventory carrying costs, from an input-output device and for storing the schedule and task data in the memory; generating means for generating initial schedule data, the generating means having means for retrieving the schedule and task data from the memory, means for processing the retrieved data in the central processing unit to generate initial schedule data wherein the workers are scheduled to perform tasks at work centers, and means for storing the initial schedule data in the memory; enhancing means for enhancing the initial schedule data, the enhancing means having means for retrieving the initial schedule data from the memory, means for processing the retrieved data in the central processing unit to generate enhanced schedule data wherein the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of the other tasks, and means for storing the enhanced schedule data in the memory; and outputting means for outputting the enhanced schedule to an input-output device to effect the controlling of the allocation of the workers, work centers, and tasks.
-
-
17. A method for reallocating resources in a manufactory, the manufactory having a current allocation of resources, the resources including tasks, work centers, and workers, each task having an inventory carrying cost, the tasks including end-product tasks, each end-product task having a delayed delivery cost, the method comprising the steps of:
-
determining the current allocation of the resources in the manufactory; monitoring the factory resources to determine when a resource becomes available; when a resource becomes available, generating a new allocation of resources based on the delayed delivery costs and inventory carrying costs whereby the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of other tasks; and reallocating the resources based on the new allocation. - View Dependent Claims (18)
-
-
19. A task and work center allocating apparatus for allocating tasks, and work centers among workers, the system comprising:
-
means for storing schedule and task information, delayed delivery costs, and inventory carrying costs; means for generating an initial schedule based on the schedule and task information whereby workers are assigned to perform tasks at work centers; means for modifying the initial schedule based on the delayed delivery costs and inventory carrying costs whereby the start of at least two tasks are delayed when the delayed delivery cost of at least one end-product task is offset by the inventory carrying cost savings due to delaying the start of other tasks; and means for assigning a worker to perform a task at a work center in accordance with the modified initial schedule.
-
Specification