Peak demand limiter and sequencer

  • US 5,581,132 A
  • Filed: 08/04/1995
  • Issued: 12/03/1996
  • Est. Priority Date: 08/04/1995
  • Status: Expired due to Fees
First Claim
Patent Images

1. A system for monitoring incoming electric power being consumed in a facility and for interrupting the flow of electric power within the facility to selected power consuming loads when a preselected peak incoming power load is exceeded for a first preselected time period comprising:

  • first means for producing a power load signal proportional to the instantaneous total incoming amperage flowing into the facility;

    a peak demand limiter including;

    second means for receiving said power load signal and for providing a load shed control signal after said first preselected time period during which said power load signal has exceeded said preselected peak load;

    third means for receiving said load shed control signal and for then sequentially transmitting independent first and second equipment shut-off signals each of short pulsed duration through a first and second phase power transmission line, respectively, of a multi-phase power line within the facility supplying electrical current to an electrical circuit breaker panel within the facility;

    said third means also for repeating the sequential transmittal of said first and second shut-off signals through the first and second phase power transmission line;

    a remote receiver connected between the circuit breaker panel and a first power consuming load including;

    fourth means for receiving each said shut-off signal and for opening a first relay of the first power consuming load to interrupt electrical power being supplied from the circuit breaker panel to the first power consuming load;

    fifth means for closing said first relay to restore electrical power to the first power consuming load after a second preselected time period.

View all claims
  • 0 Assignments
Timeline View
Assignment View
    ×
    ×