Method and apparatus for monitoring hydroelectric facility performance costs
First Claim
1. A method for monitoring performance of a hydroelectric power generation facility, the method comprising the steps of:
- (a) storing in a memory circuit a predetermined reference signal for an operating parameter of the power generation facility, the predetermined reference signal representing a desired operating level for the parameter, the operating parameter being selected from a group comprising differential head from headwater to tailwater, power generation level, cavitation, and trash rack loss;
(b) sensing a current level of the operating parameter and generating a sensed parameter signal representative thereof;
(c) comparing the sensed parameter signal to the predetermined reference signal for the parameter to determine a parameter difference signal; and
(d) applying an economic cost factor to the parameter difference signal to generate an economic cost estimate value, the economic cost estimate value representing the economic cost of operation of the facility at the current level of the operating parameter compared to the desired operating level.
1 Assignment
0 Petitions
Accused Products
Abstract
A method and system are provided for monitoring performance parameters of a hydroelectric power generation facility and determining economic impact of operating the facility at levels other than predetermined reference levels. Optimal or desired levels of parameters of interest are stored in a memory circuit coupled to a central processing circuit. Actual values for the parameters of interest are sensed and communicated to the central processing circuit. Various monitoring circuit modules may be created for specific parameters of interest. The monitoring circuit modules compare the reference values to corresponding actual values and determine deviations from the desired parameter levels. A costing circuit applies an economic impact factor to the deviation values to determine the economic impact of the deviation. The technique may be used to evaluate past or present performance, predict future performance, schedule maintenance, predict payback for plant improvements and the like.
25 Citations
20 Claims
-
1. A method for monitoring performance of a hydroelectric power generation facility, the method comprising the steps of:
-
(a) storing in a memory circuit a predetermined reference signal for an operating parameter of the power generation facility, the predetermined reference signal representing a desired operating level for the parameter, the operating parameter being selected from a group comprising differential head from headwater to tailwater, power generation level, cavitation, and trash rack loss; (b) sensing a current level of the operating parameter and generating a sensed parameter signal representative thereof; (c) comparing the sensed parameter signal to the predetermined reference signal for the parameter to determine a parameter difference signal; and (d) applying an economic cost factor to the parameter difference signal to generate an economic cost estimate value, the economic cost estimate value representing the economic cost of operation of the facility at the current level of the operating parameter compared to the desired operating level. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8)
-
-
9. A method for determining economic impact of operation of a hydroelectric power generation facility at conditions other than predetermined reference conditions comprising the steps of:
-
(a) storing in a memory circuit a reference value for an operating parameter of the facility, the reference value representing a reference operating level for the parameter, the operating parameter being selected from a group comprising differential head from headwater to tailwater, power generation level, cavitation, and trash rack loss; (b) monitoring operation of the facility and generating an actual value for the operating parameter; (c) comparing the reference value to the actual value to determine a difference value; (d) deriving an economic impact value from the difference value by applying an economic impact factor thereto; and (e) storing the economic impact value in the memory circuit. - View Dependent Claims (10, 11, 12, 13, 14)
-
-
15. A system for determining economic impact of operation of a hydroelectric power generation facility at an operating level other than a predetermined reference operating level for an operating parameter, the facility including a dam extending across a stream and at least one turbine generator supported within the dam for generating electrical power from water flow from an upstream side to a downstream side of the dam, the system comprising:
-
a memory circuit, the memory circuit storing a reference parameter value representative of the reference operating level for the operating parameter, the operating parameter being selected from a group comprising differential head from the upstream side to the downstream side of the dam, power generation level, cavitation, and trash rack loss; a sensor, the sensor being situated in the facility to detect actual levels of the operating parameter and to generate an actual parameter value representative thereof; and a controller coupled to the memory circuit and to the sensor, the controller comparing the reference parameter value and the actual parameter value and applying an economic impact factor thereto to generate an economic impact value representative of the economic impact of operation of the facility at the actual level of the parameter rather than the reference level. - View Dependent Claims (16, 17, 18, 19, 20)
-