Method for improving the feasibility of a drilling rig of jack-up type and a drilling rig of jack-up type
First Claim
1. A method of improving the feasibility of a jack-up drilling rig, said drilling rig comprising a frame with a working deck and a substantially plane shaped bottom, at least a part of power production and operating equipment being arranged in said frame;
- at least three feet provided on said frame, said feet being arranged to move vertically with respect to said frame by means of lifting devices between a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom;
a drilling unit provided on said frame, said drilling unit being moveable in a horizontal direction with respect to said frame between a transportation position wherein said drilling unit is substantially above said frame and a drilling position wherein said drilling unit is substantially outside said frame; and
a blow arrangement, said method comprising the steps of;
providing an air space, defined by side walls and an open lower end portion, below said plane shaped bottom;
filling said air space with air via said blow arrangement to form an air-bed, at least when said feet are moving;
discharging said air space for transporting said drilling rig.
0 Assignments
0 Petitions
Accused Products
Abstract
A method and apparatus for an improved drilling rig of jack-up type is provided. The drilling rig has a frame part comprising a working deck and an essentially plane-shaped bottom. Three feet are provided in the frame and are operated by lifting devices. The feet support the frame on the sea bottom during a drilling operation and are lifted off the sea bottom when the drilling rig is transported. A drilling unit is movably arranged on the frame part and can be moved substantially outside the frame during a drilling operation. A residence unit is also provided on the frame and is movable in a direction opposite that of the drilling unit at least during the drilling operation. An air bed is blown into an airspace which is arranged below the frame part of the drilling rig. The air bed is dischargeable for transportation of the drilling rig.
-
Citations
15 Claims
-
1. A method of improving the feasibility of a jack-up drilling rig, said drilling rig comprising a frame with a working deck and a substantially plane shaped bottom, at least a part of power production and operating equipment being arranged in said frame;
- at least three feet provided on said frame, said feet being arranged to move vertically with respect to said frame by means of lifting devices between a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom;
a drilling unit provided on said frame, said drilling unit being moveable in a horizontal direction with respect to said frame between a transportation position wherein said drilling unit is substantially above said frame and a drilling position wherein said drilling unit is substantially outside said frame; and
a blow arrangement, said method comprising the steps of;providing an air space, defined by side walls and an open lower end portion, below said plane shaped bottom; filling said air space with air via said blow arrangement to form an air-bed, at least when said feet are moving; discharging said air space for transporting said drilling rig. - View Dependent Claims (2, 3, 4)
- at least three feet provided on said frame, said feet being arranged to move vertically with respect to said frame by means of lifting devices between a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom;
-
5. A method of improving the function of a jack-up drilling rig, said drilling rig comprising a frame with a working deck and a substantially plane shaped bottom, at least a part of power production and operating equipment being arranged in said frame;
- at least three feet provided on said frame, said feet are arranged to move vertically with respect to said frame by means of lifting devices between a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom;
a drilling unit provided on said frame, said drilling unit being moveable in a horizontal direction with respect to said frame between a transportation position wherein said drilling unit is substantially above said frame and a drilling position wherein said drilling unit is substantially out side said frame;
a residence unit located on said frame and a helicopter deck connected to said residence unit, said method comprising the step of;providing an emergency exit at a lower edge of said residence unit; and moving said residence unit comprising said helicopter deck away from said drilling unit, at least during drilling, such that said emergency exit moves outside said frame. - View Dependent Claims (6, 7)
- at least three feet provided on said frame, said feet are arranged to move vertically with respect to said frame by means of lifting devices between a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom;
-
8. A jack-up drilling rig comprising:
-
a frame with a working deck and a substantially plane shaped bottom, at least a part of power production and operating equipment being arranged in said frame; at least three feet provided on said frame, said feet are arranged to move vertically with respect to said frame by means of lifting devices, said feet are moveable from a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom; a drilling unit provided on said frame, said drilling unit being moveable in a horizontal direction with respect to said frame, said drilling unit moveable from a transportation position substantially above said frame and a drilling position substantially outside said frame; a blow arrangement; an air space, defined by side walls and an open lower end portion, arranged under said plane shaped bottom, said air space being dischargeable during said transportation phase and inflatable via said blow arrangement to form an air bed at least during movement of said feet. - View Dependent Claims (9, 10, 11, 12)
-
-
13. A jack-up drilling rig comprising:
-
a frame with a working deck and a substantially plane shaped bottom, at least a part of power production and operating equipment being arranged in said frame; at least three feet provided on said frame, said feet are arranged to move vertically with respect to said frame by means of lifting devices, said feet are moveable from a standby position in which said feet are elevated for transportation of said drilling rig and a working position in which said feet support said frame on the sea bottom; a drilling unit provided on said frame, said drilling unit being moveable in a horizontal direction with respect to said frame between a transportation position wherein said drilling unit is substantially above said frame and a drilling position wherein said drilling unit is substantially outside said frame; a residence unit having an emergency exit arranged at a lower edge, said residence unit being movable in a direction away from said drilling unit, at least during drilling, whereby said emergency exit is moved outside said frame; and a helicopter deck connected to said residence unit and being movable in connection with said residence unit. - View Dependent Claims (14, 15)
-
Specification