Front control system, area setting method and control panel for construction machine
First Claim
1. A front control system equipped on a construction machine comprising a multi-articulated front device made up of a plurality of front members rotatable in the vertical direction, a plurality of hydraulic actuators for driving respectively said plurality of front members, and a plurality of hydraulic control valves driven in accordance with respective operation signals input from a plurality of operating means for controlling flow rates of a hydraulic fluid supplied to said plurality of hydraulic actuators, said front control system controlling said front device to be moved in a preset area, wherein said front control system comprises:
- first area setting means having a direct setting switch for setting an area where said front device is allowed to move, by direct teaching in response to an instruction from said direct setting switch, second area setting means having a numeral input switch for setting an area where said front device is allowed to move, by inputting a numeral value through said numeral input switch, and setting selection means for selecting one of said first area setting means and said second area setting means.
1 Assignment
0 Petitions
Accused Products
Abstract
A setting device for a front control system for a construction machine includes a direct setting switch for instructing a direct teaching setting, a numeral input key consisting of up- and down-keys for instructing a numeral input setting, a setting changeover switch for changing over a setting mode from the direct teaching setting to the numeral input setting, an LED lighting up when the setting changeover switch is pushed, an area limiting switch for starting an area limiting excavation control, an LED lighting up when the area limiting switch is pushed, and a display screen for indicating the position of a bucket end of a front device in terms of a numeral value when the setting changeover switch is not pushed, and indicating the numeral value input with the numeral input with the numeral input setting when the setting changeover switch is pushed.
-
Citations
24 Claims
-
1. A front control system equipped on a construction machine comprising a multi-articulated front device made up of a plurality of front members rotatable in the vertical direction, a plurality of hydraulic actuators for driving respectively said plurality of front members, and a plurality of hydraulic control valves driven in accordance with respective operation signals input from a plurality of operating means for controlling flow rates of a hydraulic fluid supplied to said plurality of hydraulic actuators, said front control system controlling said front device to be moved in a preset area, wherein said front control system comprises:
-
first area setting means having a direct setting switch for setting an area where said front device is allowed to move, by direct teaching in response to an instruction from said direct setting switch, second area setting means having a numeral input switch for setting an area where said front device is allowed to move, by inputting a numeral value through said numeral input switch, and setting selection means for selecting one of said first area setting means and said second area setting means. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 24)
a temporary cancel switch, and control cancel means for temporarily cancelling control of said front device performed by said control means when said temporary cancel switch is pushed. -
11. A front control system for a construction machine according to claim 10, wherein said temporary cancel switch is provided on a lever grip of one of said plurality of control lever means.
-
12. A front control system for a construction machine according to claim 10, wherein said direct setting switch and said numeral input switch are provided on a box-type control panel installed in a cab, and said temporary cancel switch is provided on a lever grip of one of said plurality of control lever means.
-
13. A front control system for a construction machine according to claim 12, wherein said first area setting means further includes another direct setting switch provided on said lever grip for direct setting of the area where said front device is allowed to move.
-
14. A front control system for a construction machine according to claim 13, wherein said temporary cancel switch and said direct setting switch both provided on said lever grip have surface configurations different from each other.
-
15. A front control system for a construction machine according to claim 11, wherein said control lever means on which said temporary cancel switch is provided is the control lever means for a boom of a hydraulic excavator.
-
16. A front control system for a construction machine according to claim 10, wherein said control cancel means comprises means for interrupting modification of the operation signal made by said control means when said temporary cancel switch is pushed.
-
17. A front control system for a construction machine according to claim 10, wherein said control cancel means comprises means for temporarily changing the set position of a boundary of said area to a value representing a position to which said front control device cannot reach, when said temporary cancel switch is pushed.
-
24. A front control system for a construction machine according to claim 12, wherein said control lever means on which said temporary cancel switch is provided is the control lever means for a boom of a hydraulic excavator.
-
-
18. An area setting method for use in a front control system under which a multi-articulated front device made up of a plurality of front members rotatable in the vertical direction is controlled so that said front device is moved in a preset area, comprising the steps of:
moving said front device to a position as a reference, storing the position by direct teaching, setting a depth by inputting a numeral value with the stored position as a base, and setting an area where said front device is allowed to move, in accordance with a numeral value resulted from said depth setting.
-
19. A control panel of a front control system equipped on a construction machine comprising a multi-articulated front device made up of a plurality of front members rotatable in the vertical direction, a plurality of hydraulic control valves driven in accordance with respective operation signals input from a plurality of operating means for controlling flow rates of a hydraulic fluid supplied to said plurality of hydraulic actuators, said front control system controlling said front device to be moved in a preset area, wherein said control panel comprises:
-
a direct setting switch for instructing by direct teaching setting of an area where said front device is allowed to move, a numeral input switch for instructing by input of a numeral value setting of an area where said front device is allowed to move, and a setting changeover switch for selecting one of the setting instructions from said direct setting switch and said numeral input switch. - View Dependent Claims (20, 21, 22, 23)
-