1. A method for supporting a pipeline in a trench comprising:
- placing a plurality of support benches at spaced intervals along the length of said trench, said benches being designed to fail when a predetermined weight has been placed thereon;
placing said pipeline on said benches;
filling space under said pipeline, between said benches and around said pipeline to a predetermined height with a padding material;
applying a fill material over the padding material in said trench;
filling said pipeline with water; and
allowing said plurality of support benches to fail such that said padding material provides support for said pipeline.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for supporting an underground pipeline in an excavated trench. The method involves supporting the pipeline on specially-designed support benches at spaced intervals. The benches are designed to fail when exposed to a predetermined load, which load will be placed on the benches at some point during the backfilling of the trench or when the pipeline undergoes hydrostatic testing. When the benches fail, the fill under the pipeline is compacted and thereby supports the pipeline in lieu of the support benches.
-
Citations
19 Claims
-
1. A method for supporting a pipeline in a trench comprising:
-
placing a plurality of support benches at spaced intervals along the length of said trench, said benches being designed to fail when a predetermined weight has been placed thereon;
placing said pipeline on said benches;
filling space under said pipeline, between said benches and around said pipeline to a predetermined height with a padding material;
applying a fill material over the padding material in said trench;
filling said pipeline with water; and
allowing said plurality of support benches to fail such that said padding material provides support for said pipeline. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16)
checking each of said support benches to insure that said pipeline rests thereon; and
installing shims on those of said benches which are not in contact with said pipeline, such that said pipeline contacts said shims.
-
-
5. The method of claim 1 wherein said step of filling with said padding material comprises:
-
introducing said padding material on both sides of said pipeline; and
filling areas under said pipeline before said padding material fills areas between said pipeline and the walls of said trench.
-
-
6. The method of claim 5 wherein said padding material is a uniform material.
-
7. The method of claim 6 wherein said padding material is relatively rock-free.
-
8. The method of claim 1 wherein said step of allowing said plurality of benches to fail includes the step of allowing failure anytime after said padding material is introduced into said trench.
-
9. The method of claim 8 wherein said plurality of benches are designed to support a weight of said pipeline when said pipeline is empty, and to fail when additional weight is applied.
-
10. The method of claim 9 wherein said plurality of benches fail under at least one of weight of said fill material placed on the pipeline, and a combined weight of said fill material placed on the pipeline and water placed into the pipeline.
-
11. The method of claim 1 wherein said benches are constructed of a rigid material and are designed to structurally fail at a predetermined weight.
-
12. The method of claim 1 wherein said benches are constructed of a deformable material such that said benches compress when loaded.
-
13. The method of claim 12 wherein said benches are comprised of expandable polystyrene.
-
14. The method of claim 12 wherein said benches compress enough to allow said padding material to become compacted.
-
15. The method of claim 14 wherein said benches compress to a level within the trench of said compacted padding material.
-
16. The method of claim 15 wherein said pipeline is supported along its entire length by compacted padding material and compressed benches.
-
17. A method for supporting a pipeline in a trench comprising:
-
placing a plurality of support benches at spaced intervals along the length of said trench, said benches being designed to fail when a predetermined weight has been placed thereon;
placing said pipeline on said benches;
filling space under said pipeline, between said benches and around said pipeline to a predetermined height with a padding material; and
applying force to the pipeline sufficient to cause said plurality of support benches to fail such that said padding material provides support for said pipeline. - View Dependent Claims (18, 19)
-
Specification