Dual path scheduling method

  • US 6,714,829 B1
  • Filed: 06/22/2000
  • Issued: 03/30/2004
  • Est. Priority Date: 06/22/2000
  • Status: Expired due to Fees
First Claim
Patent Images

1. A method of scheduling a project consisting of a plurality of tasks, said method comprising the steps of:

  • identifying critical tasks of the project;

    identifying para-critical tasks of the project;

    displaying the critical tasks in a visually perceptible manner with the critical tasks ranked in chronological order;

    displaying the identified para-critical tasks in a visually perceptible manner adjacent to the displayed critical tasks;

    establishing target finish dates for the displayed critical tasks and displaying a target finish date for each of the displayed critical tasks adjacent to the respective displayed critical task;

    monitoring performance of the displayed critical tasks to establish actual completion dates of the displayed critical tasks;

    displaying the actual completion date of each displayed critical task adjacent to the associated displayed critical task upon completion thereof; and

    adjusting the target finish dates for all subsequent displayed critical tasks to reflect any variance between the target finish date and the actual finish date of a displayed critical task.