Forecast test-out of probed fabrication by using dispatching simulation method
First Claim
1. A method for scheduling fabrication and testing of product within a manufacturing line comprising the steps of:
- a) creating a process equipment model for equipment and processes within said manufacturing line;
b) generating a potential product dispatch schedule for the product to be fabricated within said manufacturing line;
c) defining an equipment dispatch schedule for equipment employed in fabrication and testing of said product to be fabricated according to said product dispatch schedule;
d) simulating said potential product dispatch schedule;
e) determining if said potential product dispatch schedule is optimized;
f) if said product dispatch schedule is not optimized, generating another potential product dispatch schedule for said product and performing steps b) through e); and
g) if said product dispatch schedule is optimized, dispatching said products for fabrication and test according to said schedule;
wherein the process equipment model is described as a Petri-Net model to express the function of the process equipment during fabrication and test of said product.
1 Assignment
0 Petitions
Accused Products
Abstract
A method and apparatus for simulating the functioning of various configurations of fabrication and test equipment within a manufacturing line creates a schedule for dispatching of the production lots to the manufacturing line. Based on the product mix forecast, the product volume forecast, the predicted sales schedule, the sales confidence, the actual sales order descriptions, and the product delivery schedule, a potential product dispatch schedule is established that enables a product to be fabricated within the manufacturing line. An equipment dispatch schedule for equipment employed in fabrication and testing of the product to be fabricated is defined according to the product dispatch schedule. The potential product dispatch schedule is then simulated based on the process and test equipment model. Upon completion of the simulation, the potential product dispatch schedule is assessed for optimization.
50 Citations
20 Claims
-
1. A method for scheduling fabrication and testing of product within a manufacturing line comprising the steps of:
-
a) creating a process equipment model for equipment and processes within said manufacturing line;
b) generating a potential product dispatch schedule for the product to be fabricated within said manufacturing line;
c) defining an equipment dispatch schedule for equipment employed in fabrication and testing of said product to be fabricated according to said product dispatch schedule;
d) simulating said potential product dispatch schedule;
e) determining if said potential product dispatch schedule is optimized;
f) if said product dispatch schedule is not optimized, generating another potential product dispatch schedule for said product and performing steps b) through e); and
g) if said product dispatch schedule is optimized, dispatching said products for fabrication and test according to said schedule;
wherein the process equipment model is described as a Petri-Net model to express the function of the process equipment during fabrication and test of said product. - View Dependent Claims (2, 3, 4)
-
-
5. An apparatus for scheduling fabrication and testing of product within a manufacturing line comprising:
-
a) means for creating a process equipment model for equipment and processes within said manufacturing line;
b) means for generating a potential product dispatch schedule for product to be fabricated within said manufacturing line;
c) means for defining an equipment dispatch schedule for equipment employed in fabrication and testing of said product to be fabricated according to said product dispatch schedule;
d) means for simulating said potential product dispatch schedule;
e) means for determining if said potential product dispatch schedule is optimized;
f) means for generating another potential product dispatch schedule for said product and activating the means of b) through e), if said product dispatch schedule is not optimized; and
g) means for dispatching said products for fabrication and test according to said schedule, if said product dispatch schedule is optimized;
wherein the process equipment model is described as a Petri-Net model to express the function of the process equipment during fabrication and test of said product. - View Dependent Claims (6, 7, 8)
-
-
9. A manufacturing and test scheduling system for scheduling and dispatch of the fabrication of product and of verification of function of said product comprising:
-
a product requirement and allocation generator which receives product forecast information, product order information, product process equipment information to generate a product lot scheduling;
a manufacturing equipment model generator which receives a product capability and capacity schedule and the product process equipment information to generate a simulation model for fabrication and testing of said product; and
a manufacturing simulator which receives an equipment dispatch algorithm and is in communication with said manufacturing equipment model generator to receive said simulation model and in communication with said product requirement and allocation generator to receive a candidate product lot scheduling to simulate and simulation model using said candidate product lot scheduling to determine if said product lot scheduling and said equipment dispatch algorithm are optimized, whereby;
if said product lot scheduling is not optimized, informing said product requirement and allocation generator to modify said product lot scheduling, if said product lot scheduling is optimized, initiating dispatching said product for fabrication and testing; and
if said equipment dispatch algorithm is not optimized, modifying said equipment dispatch algorithm and re-simulating said simulation model to determine if said product lot scheduling and said equipment dispatch algorithm are optimized. - View Dependent Claims (10, 11, 12)
-
-
13. A manufacturing system for the fabrication and testing of product comprising:
-
manufacturing and test scheduling system for scheduling and dispatch of the fabrication of product and of verification of function of said product comprising;
a product requirement and allocation generator which receives product forecast information, product order information, product process equipment information to generate a product lot scheduling;
a manufacturing equipment model generator which receives a product capability and capacity schedule and the product process equipment information to generate a simulation model for fabrication and testing of said product; and
a manufacturing simulator which receives an equipment dispatch algorithm and is in communication with said manufacturing equipment model generator to receive said simulation model and in communication with said product requirement and allocation generator to receive a candidate product lot scheduling to simulate and simulation model using said candidate product lot scheduling to determine if said product lot scheduling and said equipment dispatch algorithm are optimized, whereby;
if said product lot scheduling is not optimized, informing said product requirement and allocation generator to modify said product lot scheduling, if said product lot scheduling is optimized, initiating dispatching said product for fabrication and testing; and
if said equipment dispatch algorithm is not optimized, modifying said equipment dispatch algorithm and re-simulating said simulation model to determine if said product lot scheduling and said equipment dispatch algorithm are optimized. - View Dependent Claims (14, 15, 16)
-
-
17. A medium for retaining a computer program for scheduling fabrication and testing of product within a manufacturing line, said computer program executed on a computer system performs the program process comprising the steps of:
-
a) creating a process equipment model for equipment and processes within said manufacturing line;
b) generating a potential product dispatch schedule for product to be fabricated within said manufacturing line;
c) defining an equipment dispatch schedule for equipment employed in fabrication and testing of said product to be fabricated according to said product dispatch schedule;
d) simulating said potential product dispatch schedule;
e) determining if said potential product dispatch schedule is optimized;
f) if said product dispatch schedule is not optimized, generating another potential product dispatch schedule for said product and performing steps b) through e); and
g) if said product dispatch schedule is optimized, dispatching said products for fabrication and test according to said schedule;
wherein the process equipment model is described as a Petri-Net model to express the function of the process equipment during fabrication and test of said product. - View Dependent Claims (18, 19, 20)
-