Partial discharge detection test link, partial discharge detection system and methods for detecting partial discharge on a power cable
First Claim
1. A method for detecting partial discharge on an energized power cable having an accessory interposed therein, the accessory including a first accessory component and a second accessory component coupled to each other and connected by a service link, the method comprising the steps of:
- providing a test link having a built-in partial discharge sensor;
removing the service link;
replacing the service link with the test link by directly electrically connecting the first accessory component and the second accessory component together using the test link thereby providing electrical communication between the first and second accessory components through the test link;
detecting the partial discharge of the energized power cable at the test link by generating partial discharge electrical signals representative of the detected partial discharge; and
interpreting the partial discharge electrical signals in a manner to measure the partial discharge of the energized power cable.
3 Assignments
0 Petitions
Accused Products
Abstract
A partial discharge detection test link and system is disclosed to detect partial discharge of a power cable accessory. The power cable accessory includes a first accessory component and a second accessory component connected to each other. The partial discharge detection test link is a permanent or temporary substitute for a conventional service link, connects directly across the power cable accessory and includes a conductor member and a partial discharge sensor. The conductor member has an electrically conductive element and an insulation surrounding and extending along the electrically conductive element. The electrically conductive element is electrically connected directly between the first and second accessory components. The partial discharge sensor is disposed about the conductor member and has the electrically conductive element as a primary winding and a secondary winding with the insulation positioned between the primary and secondary windings.
16 Citations
8 Claims
-
1. A method for detecting partial discharge on an energized power cable having an accessory interposed therein, the accessory including a first accessory component and a second accessory component coupled to each other and connected by a service link, the method comprising the steps of:
-
providing a test link having a built-in partial discharge sensor;
removing the service link;
replacing the service link with the test link by directly electrically connecting the first accessory component and the second accessory component together using the test link thereby providing electrical communication between the first and second accessory components through the test link;
detecting the partial discharge of the energized power cable at the test link by generating partial discharge electrical signals representative of the detected partial discharge; and
interpreting the partial discharge electrical signals in a manner to measure the partial discharge of the energized power cable. - View Dependent Claims (2)
-
-
3. A method for detecting partial discharge on a plurality of energized power cables with each energized power cable interconnected by an accessory having a first accessory component and a second accessory component coupled to each other and connected by a service link, the plurality of energized power cables disposed apart from one another in a juxtaposed relationship and positioned in an enclosure defined by an arrangement of walls, the method comprising the steps of:
-
providing at least one electrically insulative barrier and a plurality of test links;
replacing the service links with test links by directly electrically connecting the respective ones of the first accessory components and the second accessory components to each other using respective ones of the plurality of test links thereby providing direct electrical communication between the respective ones of the connected first and second accessory components;
positioning the at least one electrically insulative barrier between juxtaposed ones of the plurality of energized power cables so that flashover is inhibited;
detecting partial discharge of the plurality of energized power cables at respective ones of the test links by generating partial discharge electrical signals representative of the detected partial discharge of the respective energized power cables;
converting the partial discharge electrical signals adjacent the enclosure to alternative energy signals representative of the partial discharge electrical signals;
transmitting the alternative energy signals to a location remote from the enclosure; and
interpreting the alternative energy signals at the remote location in a manner to measure the partial discharge of the respective energized power cables. - View Dependent Claims (4, 5, 6, 7)
-
-
8. A method for detecting partial discharge on an energized power cable having an accessory interposed therein, the accessory including a first accessory component and a second accessory component coupled to each other and connected by a service link that comprises a first conductor member, the method comprising the steps of:
-
providing a test link comprising a second conductor member and a built-in partial discharge sensor;
removing the service link;
replacing the service link with the test link by directly electrically connecting the first accessory component and the second accessory component together using the test link thereby providing electrical communication between the first and second accessory components through the test link;
detecting the partial discharge of the energized power cable at the test link by generating partial discharge electrical signals representative of the detected partial discharge; and
interpreting the partial discharge electrical signals in a manner to measure the partial discharge of the energized power cable.
-
Specification