1. In a power system having a power grid providing electrical power to a plurality of subscribers, the power system configured to provide advance notification to each subscriber whose electrical load is to be entirely shed from the power grid, the power system further including a plurality of providers providing electrical power services to the plurality of subscribers, and a control authority independent of said plurality of providers, said control authority determining when electrical load must be shed from the power grid, a method comprising:
- providing a notification database of the selection of which of a plurality of notification methods is desired by each said subscriber to be used for notifying at least one subscriber of the plurality of subscribers of an impending change in the connection of the entire electrical load of said at least one subscriber to the power grid;
the control authority issuing to at least one of the plurality of providers a directive to perform an operative action for shedding electrical load to the power grid wherein a performance of the operative action is only capable of being performed by said at least one provider and incapable of being performed by any said subscriber,determining which of the plurality of subscribers, is to have electrical load entirely shed from the power grid;
automatically determining from the notification database which of said plurality of notification methods are to be used for notifying said at least one subscriber of the impending change in the connection of the entire electrical load of said at least one subscriber to the power grid in response to said determining which of the plurality of subscribers is to have electrical load entirely shed from the power grid; and
,notifying said at least one subscriber by the at least one notification method in said notification database prior to performance of the operative action.
3 Assignments
0 Petitions
Accused Products
Abstract
At a first time, an authorized directive is received by the utility provider to perform an operative action for shedding load of a power system by a minimum system load value on or before a second time. The utility provider may operate the SCADA/DCS system to assist in selecting a set of circuits wherein the total circuit load value of the selection is greater than or equal to the minimum system load value. In response to circuit selection, the SCADA/DCS system selects the corresponding set of circuit breakers and consults the circuit-subscriber notification database to select a set of subscribers corresponding to the selected set of circuits. A system, product, and/or device adapted for communicating data in response to circuit selection may then be accessed by the SCADA/DCS system to communicate to the selected set of subscribers an intention of performing the operative action on or before the second time. The utility provider may then program and/or operate the SCADA/DCS system to perform the operative action upon the selected set of circuit breakers on or before said second time.
-
Citations
48 Claims
-
1. In a power system having a power grid providing electrical power to a plurality of subscribers, the power system configured to provide advance notification to each subscriber whose electrical load is to be entirely shed from the power grid, the power system further including a plurality of providers providing electrical power services to the plurality of subscribers, and a control authority independent of said plurality of providers, said control authority determining when electrical load must be shed from the power grid, a method comprising:
-
providing a notification database of the selection of which of a plurality of notification methods is desired by each said subscriber to be used for notifying at least one subscriber of the plurality of subscribers of an impending change in the connection of the entire electrical load of said at least one subscriber to the power grid; the control authority issuing to at least one of the plurality of providers a directive to perform an operative action for shedding electrical load to the power grid wherein a performance of the operative action is only capable of being performed by said at least one provider and incapable of being performed by any said subscriber, determining which of the plurality of subscribers, is to have electrical load entirely shed from the power grid; automatically determining from the notification database which of said plurality of notification methods are to be used for notifying said at least one subscriber of the impending change in the connection of the entire electrical load of said at least one subscriber to the power grid in response to said determining which of the plurality of subscribers is to have electrical load entirely shed from the power grid; and
,notifying said at least one subscriber by the at least one notification method in said notification database prior to performance of the operative action. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47)
-
-
48. In a power system having a power grid providing electrical power to a plurality of subscribers, the power system configured to provide advance notification to each subscriber whose electrical load is to be entirely shed from the power grid, the power system further including a plurality of providers providing electrical power services to the plurality of subscribers, and a control authority independent of said plurality of providers, said control authority determining when electrical load must be shed from the power grid, an apparatus comprising:
-
a notification database of the selection of which of a plurality of notification methods is desired by each said subscriber to be used for notifying at least one subscriber of the plurality of subscribers of an impending change in the connection of the entire electrical load of said at least one subscriber to the power grid; means for the control authority issuing to at least one of the plurality of providers a directive to perform an operative action for shedding electrical load to the power grid wherein a performance of the operative action is only capable of being performed by said at least one provider and incapable of being performed by any said subscriber; means for determining which of the plurality of subscribers is to have electrical load entirely shed from the power grid; means for determining from the notification database which of said plurality of notification methods are to be used for notifying said at least one subscriber of the impending change in the connection of the entire electrical load of said at least one subscriber to the power grid in response to said determining which of the plurality of subscribers is to have electrical load entirely shed from the power grid; and
,means for notifying said at least one subscriber by the at least one notification method in said notification database prior to performance of the operative action.
-