Method and system for displaying an image instead of data
First Claim
1. A method in a computer implemented project information management system, the method comprising:
- providing a project having summary tasks and non-summary tasks, each summary task and non-summary task having a cost field with project cost information and each summary task including a plurality of non-summary tasks;
for each summary task and non-summary task, receiving from a user a display option indicating whether to display text data or graphical indicators for the cost field;
receiving from the user a summary under budget threshold, a summary under budget graphical indicator, a summary over budget threshold, and a summary over budget graphical indicator for summary data contained in the cost field; and
receiving from the user a non-summary under budget threshold, a non-summary under budget graphical indicator, a non-summary over budget threshold, and a non-summary over budget graphical indicator for non-summary data contained in the cost field, wherein the received thresholds and indicators can be different for each summary task and non-summary task;
validating and storing the received thresholds, indicators, and display option;
processing the cost field for each summary task and non-summary task;
when processing the cost field for each summary task and non-summary task,determining whether the display option indicates displaying graphical indicators or text data for the field;
if the display option indicates to display text data, displaying text data for the cost field;
if the display option indicates to display graphical indicators and the cost field contains summary data,retrieving the stored summary under budget and summary over budget thresholds;
comparing the project cost information contained in the cost field with the summary under budget threshold;
if the project cost information is less than the under budget threshold, displaying the summary under budget graphical indicator;
comparing the project cost information contained in the cost field with the summary over budget;
if the project cost information threshold is greater than the summary over budget threshold, displaying the summary over budget indicator;
if the display option indicates to display graphical indicators and the cost field contains non-summary data,retrieving the stored non-summary under budget and summary over budget thresholds;
comparing the project cost information contained in the cost field with the non-summary under budget threshold;
if the project cost information is less than the non-summary under budget threshold, displaying the non-summary under budget graphical indicator;
comparing the project cost information contained in the cost field with the non-summary over budget threshold; and
if the project cost information is greater than the non-summary over budget threshold, displaying the non-summary over budget indicator.
2 Assignments
0 Petitions
Accused Products
Abstract
Displaying graphical indicators, instead of data, based on user-defined conditions. The user can specify conditions for displaying graphical indicators instead of actual data by specifying a test, values, and an image. The graphical indicators can be pre-assigned images that are dynamically applied based on the underlying text or numeric data values. Graphical indicators allow the user to visually represent data types or categories with graphics, based on the user'"'"'s conditions. Different conditions can be specified for a given data field and each condition can be associated with a particular graphical indicator. Prioritized processing of data conditions allow for complex control of which indicator will be displayed to visually represent the data. When the underlying data in a field changes, the criteria can be reapplied and the field dynamically updated to the appropriate indicator.
-
Citations
20 Claims
-
1. A method in a computer implemented project information management system, the method comprising:
-
providing a project having summary tasks and non-summary tasks, each summary task and non-summary task having a cost field with project cost information and each summary task including a plurality of non-summary tasks; for each summary task and non-summary task, receiving from a user a display option indicating whether to display text data or graphical indicators for the cost field; receiving from the user a summary under budget threshold, a summary under budget graphical indicator, a summary over budget threshold, and a summary over budget graphical indicator for summary data contained in the cost field; and receiving from the user a non-summary under budget threshold, a non-summary under budget graphical indicator, a non-summary over budget threshold, and a non-summary over budget graphical indicator for non-summary data contained in the cost field, wherein the received thresholds and indicators can be different for each summary task and non-summary task; validating and storing the received thresholds, indicators, and display option; processing the cost field for each summary task and non-summary task; when processing the cost field for each summary task and non-summary task, determining whether the display option indicates displaying graphical indicators or text data for the field; if the display option indicates to display text data, displaying text data for the cost field; if the display option indicates to display graphical indicators and the cost field contains summary data, retrieving the stored summary under budget and summary over budget thresholds; comparing the project cost information contained in the cost field with the summary under budget threshold; if the project cost information is less than the under budget threshold, displaying the summary under budget graphical indicator; comparing the project cost information contained in the cost field with the summary over budget; if the project cost information threshold is greater than the summary over budget threshold, displaying the summary over budget indicator; if the display option indicates to display graphical indicators and the cost field contains non-summary data, retrieving the stored non-summary under budget and summary over budget thresholds; comparing the project cost information contained in the cost field with the non-summary under budget threshold; if the project cost information is less than the non-summary under budget threshold, displaying the non-summary under budget graphical indicator; comparing the project cost information contained in the cost field with the non-summary over budget threshold; and if the project cost information is greater than the non-summary over budget threshold, displaying the non-summary over budget indicator.
-
-
2. A method in a computer-implemented project information management system, the method comprising:
-
receiving a project having a plurality of tasks, each task having a cost field; receiving from a user a display option indicating whether to display text data or graphical indicators for the cost field of a task; receiving from a user an under budget threshold, a under budget graphical indicator, an over budget threshold, and an over budget graphical indicator for data contained in the cost field of the task, wherein the received thresholds and indicators can be different for each task; processing the cost field for a task; and when processing the cost field for a task, determining whether the display option indicates displaying graphical indicators or text data for the cost field of the task; when the display option indicates to display text data, displaying text data for the cost field; and when the display option indicates to display graphical indicators, when the cost field is less than the under budget threshold, displaying the under budget graphical indicator; and when the cost field is greater than the over budget threshold, displaying the over budget graphical indicator. - View Dependent Claims (3, 4, 5, 6, 7, 8, 9, 10, 11)
-
-
12. A project information management system, the system comprising:
-
a user interface that receives a project having a plurality of tasks, each task having a cost field; memory storage that for each task, stores a display option indicating whether to display text data or graphical indicators for the cost field, and that for each task with a display option indicating to display graphical indicators, stores an under budget threshold, an under budget graphical indicator, an over budget threshold, and an over budget graphical indicator for the cost field of the task, wherein the received thresholds and indicators can be different for each task; a graphical indicator engine that processes the cost field of a task, when processing the cost field for a task, determines whether the display option indicates displaying graphical indicators or text data for the cost field; when the display option indicates to display text data, displays text data for the cost field; and when the display option indicates to display graphical indicators, retrieves the stored under budget and over budget thresholds; compares project cost information contained in the cost field with the under budget threshold; when the project cost information is less than the under budget threshold, displays the under budget graphical indicator; compares the project cost information contained in the cost field with the over budget threshold; and when the project cost information is greater than the over budget threshold, displays the over budget graphical indicator. - View Dependent Claims (13, 14, 15, 16, 17, 18, 19, 20)
-