1. A method of protecting a circuit having a first circuit breaker and a second circuit breaker downstream of said first circuit breaker, the method comprising:
- detecting a fault in said circuit, said fault being downstream of said second circuit breaker;
determining a dynamic delay time for opening said first circuit breaker; and
opening said first circuit breaker after said dynamic delay time has elapsed,wherein determining said dynamic delay time comprises monitoring electrical parameters of said circuit and communicating said electrical parameters over a network to a microprocessor, said microprocessor being configured to operate said first and second circuit breakers, wherein said dynamic delay time is based at least in part on a clearing time of said second circuit breaker.
3 Assignments
0 Petitions
Accused Products
Abstract
A circuit protection system is provided that provides a dynamic delay time to an upstream circuit breaker if a fault is detected in a circuit where the dynamic delay time can be based upon the location of the fault, such as the nearest downstream circuit breaker. A control processing unit can determine a dynamic delay time for opening a first circuit breaker if a fault is detected in the circuit. The control processing unit delays opening the first circuit breaker until after the dynamic delay time has elapsed to provide an opportunity for the nearest circuit breaker to clear the fault.
275 Citations
30 Claims
-
1. A method of protecting a circuit having a first circuit breaker and a second circuit breaker downstream of said first circuit breaker, the method comprising:
-
detecting a fault in said circuit, said fault being downstream of said second circuit breaker; determining a dynamic delay time for opening said first circuit breaker; and opening said first circuit breaker after said dynamic delay time has elapsed, wherein determining said dynamic delay time comprises monitoring electrical parameters of said circuit and communicating said electrical parameters over a network to a microprocessor, said microprocessor being configured to operate said first and second circuit breakers, wherein said dynamic delay time is based at least in part on a clearing time of said second circuit breaker. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A method of protecting a circuit having a first circuit breaker arranged upstream of a plurality of second circuit breakers, the method comprising:
-
detecting a fault in said circuit; determining a location of said fault; determining a dynamic delay time for opening said first circuit breaker based at least in part upon said location of said fault; and delaying opening said first circuit breaker until after said dynamic delay time has elapsed, wherein determining said location of said fault comprises determining a nearest breaker upstream to said fault of said plurality of second circuit breakers, said nearest breaker being nearest to said fault and upstream of said fault, and wherein said dynamic delay time is based at least in part upon a clearing time of said nearest breaker. - View Dependent Claims (9, 10, 11, 12, 13, 14, 15, 16, 17)
-
-
18. A protection system coupled to a circuit having a first circuit breaker arranged upstream of a plurality of second circuit breakers, the system comprising:
-
a network and at least one control processing unit operatively controlling said first circuit breaker and said plurality of second circuit breakers, said network being communicatively coupled to said circuit, said first circuit breaker, said plurality of second circuit breakers and said at least one control processing unit, wherein said at least one control processing unit determines a dynamic delay time for opening said first circuit breaker if a fault is detected in said circuit, and wherein said at least one control processing unit delays opening said first circuit breaker until after said dynamic delay time has elapsed, wherein said at least one control processing unit receives parameter signals representative of electrical parameters of said circuit, wherein said at least one control processing unit opens at least one of said second circuit breakers in response to said parameter signals if said fault is detected in said circuit and wherein said dynamic delay time is based at least in part on a location of said fault. - View Dependent Claims (19, 20, 21, 22)
-
-
23. A power distribution system comprising:
-
a circuit having a plurality of circuit breakers, at least one power source and at least one load, said plurality of circuit breakers being arranged with at least one first circuit breaker upstream of a plurality of second circuit breakers; a network; and at least one control processing unit operatively controlling said plurality of circuit breakers, said network being communicatively coupled to said at least one control processing unit and said circuit, wherein said at least one control processing unit determines a dynamic delay time for opening said at least one first circuit breaker if a fault is detected in said circuit, said dynamic delay time being based at least in part on a location of said fault and wherein said at least one control processing unit delays opening said at least one first circuit breaker until after said dynamic delay time has elapsed, wherein said at least one control processing unit receives parameter signals representative of electrical parameters of said circuit, wherein said dynamic delay time is selectively generated by said at least one control processing unit in response to said parameter signals if said fault is detected in said circuit, wherein said at least one control processing unit determines a nearest breaker upstream to said fault of said plurality of second circuit breakers and wherein said dynamic delay time is based at least in part on a clearing time of said nearest breaker. - View Dependent Claims (24, 25, 26, 27, 28, 29, 30)
-