Method and system for quantitatively assessing project risk and effectiveness
First Claim
1. A method for assessing risk on a project associated with at least one change proposal directed toward the project, the project being developed by a service provider for a client, said method comprising:
- receiving, from the client by the service provider, the at least one change proposal directed toward the project during a life cycle of the project, the change proposal requesting at least one amendment to be performed to the project being developed by the service provider;
identifying, based on the at least one amendment request, at least one artifact of the project to be potentially affected upon the change proposal being adopted; and
generating at least one metric indicative of the potential effects on the project based on said identifying the at least one artifact, the at least one metric providing an objective risk assessment for the service provider to provide the client and for allowing the service provider and the client to assess both direct and indirect risk before the at least one change proposal is adopted and to objectively make an informed business decision as to whether or not to adopt the at least one change proposal.
16 Assignments
0 Petitions
Accused Products
Abstract
A method and system for assessing risk of a change proposal on a project development, and effectiveness of a service provider to satisfy a client. The method for assessing risk may include receiving the change proposal requesting one or more amendments to be performed on the project. One or more elements of the project potentially affected upon the change proposal being approved may be identified based on the amendment(s) of the change proposal. Metric(s) indicative of the potential effects on the project based on the identified element(s) may be generated. The method for determining effectiveness may include receiving change proposals. A frequency of receipt of the change proposals being received during the course of the project may be monitored to determine effectiveness of the service provider in satisfying the client.
231 Citations
19 Claims
-
1. A method for assessing risk on a project associated with at least one change proposal directed toward the project, the project being developed by a service provider for a client, said method comprising:
-
receiving, from the client by the service provider, the at least one change proposal directed toward the project during a life cycle of the project, the change proposal requesting at least one amendment to be performed to the project being developed by the service provider; identifying, based on the at least one amendment request, at least one artifact of the project to be potentially affected upon the change proposal being adopted; and generating at least one metric indicative of the potential effects on the project based on said identifying the at least one artifact, the at least one metric providing an objective risk assessment for the service provider to provide the client and for allowing the service provider and the client to assess both direct and indirect risk before the at least one change proposal is adopted and to objectively make an informed business decision as to whether or not to adopt the at least one change proposal. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
-
10. A system for assessing risk on a project associated with at least one change proposal directed toward the project, the project being developed by a service provider for a client, said system comprising:
-
means for receiving, from the client by the service provider, the at least one change proposal directed toward the project during a life cycle of the project, the at least one change proposal requesting at least one amendment to be performed to the project being developed by the service provider; means for identifying, based on the at least one amendment request, at least one artifact of the project to be potentially affected upon the change proposal being adopted; and means for generating at least one metric indicative of the potential effects on the project based on said identifying the at least one artifact, the at least one metric providing an objective risk assessment for the service provider to provide the client and for allowing the service provider and the client to assess both direct and indirect risk before the at least one change proposal is adopted and to objectively make an informed business decision as to whether or not to adopt the at least one change proposal. - View Dependent Claims (11, 12, 13, 14, 15, 16, 17, 18)
-
-
19. A computer-readable medium having stored thereon sequences of instructions, the sequences of instructions, when executed by a processor, causes the processor to:
-
receive, from a client by a service provider, at least one change proposal directed toward a project during a life cycle of the project, the project being developed by the service provider for the client, the at least one change proposal requesting at least one amendment to be performed to the project; identify, based on the at least one amendment request, at least one artifact of the project to be potentially affected upon the change proposal being adopted; and generate at least one metric indicative of the potential effects on the project based on said identifying the at least one artifact, the at least one metric providing an objective risk assessment for the service provider to provide the client and for allowing the service provider and the client to assess both direct and indirect risk before the at least one change proposal is adopted and to objectively make an informed business decision as to whether or not to adopt the at least one change proposal.
-
Specification