Wind farm and method for operating same
First Claim
1. A wind farm with at least two wind turbines (1, 2, 3, 4) connected to a power grid, further comprisinga coupling device (7) for coupling the wind farm to the power grid,a sensor element (8) for sensing a first variable representative of said wind farm, wherein said sensor element (8) is adapted to transmit said measured first variable to said coupling device (7),a control unit (5) connected to said at least two wind turbines (1, 2, 3, 4), anda sensor unit (6) connected to said power grid and said centralized control unit (5), wherein said sensor unit (6) is adapted to measure the grid frequency of said power grid and to transmit said measured grid frequency to said control unit (5), andwherein said coupling device (7) is adapted to control a second variable of said wind farm according to said measured first variable, andwherein said control unit (5) is adapted to control the output of real power of said wind farm according to said measured grid frequency.
3 Assignments
0 Petitions
Reexamination
Accused Products
Abstract
A wind farm with at least two wind turbines (1, 2, 3, 4) connected to a power grid is provided, said wind farm further comprising a control unit (5) connected to said at least two wind turbines (1, 2, 3, 4), and a sensor unit (6) connected to said power grid and said control unit (5), wherein said sensor unit (6) is adapted to measure the grid frequency of said power grid and to transmit said measured grid frequency to said control unit (5), and wherein said control unit (5) is adapted to control the output of real power of said wind farm according to said measured grid frequency. Furthermore, a method for operating a wind farm is proposed, said method comprising the steps of measuring the grid frequency with a sensor unit, transmitting said measured grid frequency to a centralized control unit, determining whether the measured grid frequency lies outside a predetermined range, and, if the measured grid frequency lies outside said predetermined range, selecting at least one out of the at least two wind turbines comprised in said wind farm by said centralized control unit and regulating the power output of said selected at least one wind turbine.
-
Citations
18 Claims
-
1. A wind farm with at least two wind turbines (1, 2, 3, 4) connected to a power grid, further comprising
a coupling device (7) for coupling the wind farm to the power grid, a sensor element (8) for sensing a first variable representative of said wind farm, wherein said sensor element (8) is adapted to transmit said measured first variable to said coupling device (7), a control unit (5) connected to said at least two wind turbines (1, 2, 3, 4), and a sensor unit (6) connected to said power grid and said centralized control unit (5), wherein said sensor unit (6) is adapted to measure the grid frequency of said power grid and to transmit said measured grid frequency to said control unit (5), and wherein said coupling device (7) is adapted to control a second variable of said wind farm according to said measured first variable, and wherein said control unit (5) is adapted to control the output of real power of said wind farm according to said measured grid frequency.
Specification