Enterprise management system for normalization, integration and correlation of business measurements with application and infrastructure measurements

  • US 7,568,019 B1
  • Filed: 02/14/2003
  • Issued: 07/28/2009
  • Est. Priority Date: 02/15/2002
  • Status: Active Grant
First Claim
Patent Images

1. A computer-implemented method for managing a Business Operation, comprising:

  • collecting measurements from an Infrastructure Layer, wherein said Infrastructure Layer measurements are associated with said business operation;

    wherein said Infrastructure Layer includes one or more infrastructure objects upon which an Application Layer is implemented, said infrastructure objects including network, systems, storage, or middleware elements;

    concurrent with collecting measurements from said Infrastructure Layer, collecting measurements from said Application Layer, wherein Application Layer measurements are associated with said Business Operation;

    wherein said Application Layer includes one or more application objects upon which a Business Layer is implemented, said application objects including application services or application components;

    concurrent with collecting measurements from said Infrastructure Layer and said Application Layer, collecting measurements from said Business Layer, wherein said Business Layer measurements are associated with said Business Operation;

    wherein said Business Layer includes one or more business objects, said business objects including business services, business traffic, or business transactions;

    based on the measurements collected from each of the Infrastructure Layer, the Application Layer, and the Business Layer generating a first set of Events;

    wherein each Event in the first set of Events is a data structure indicating an observed state change or phenomenon occurrence at one of the Infrastructure Layer, the Application Layer, and the Business Layer;

    based on the first set of Events and a plurality of policies applied to Events in the first set of Events, generating a second set of Events;

    wherein the second set of Events includes;

    (a) a third set of Events that occurred at the Business Layer;

    (b) a fourth set of Events that occurred at the Application Layer; and

    (c) a fifth set of Events that occurred at the Infrastructure Layer;

    correlating Events from the third set of Events with Events from at least one of the fourth set of Events or the fifth set of Events;

    wherein the method is performed by one or more computing devices.