Method and system for analyzing schedule trends
First Claim
1. A method for determining a variance trend in schedule data, comprising:
- retrieving schedule data from a database, the schedule data comprising;
a task description of a task; and
a plurality of milestones associated with the task, the milestones comprising a baseline milestone associated with a baseline deadline, a first updated milestone associated with a first updated deadline, and a second updated milestone associated with a second updated deadline;
calculating, by a processor, a first variance by comparing the first updated deadline to the baseline deadline;
calculating, by the processor, a second variance by comparing the second updated deadline to the baseline deadline, the first variance associated with a time prior to that of the second variance;
automatically determining, by the processor, the variance trend in schedule data that indicates a change in variance by subtracting the second variance from the first variance, a positive variance trend indicating that the first and second updated deadlines are approaching the baseline deadline; and
automatically generating a display representing the variance trend.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for determining a variance trend in schedule data includes retrieving schedule data comprising a task description of a task and a plurality of milestones associated with the task including a baseline milestone associated with a baseline deadline, a first updated milestone associated with a first updated deadline, and a second updated milestone associated with a second updated deadline. The method further includes calculating a first variance by comparing the first updated deadline to the baseline deadline, calculating a second variance by comparing the second updated deadline to the baseline deadline, automatically determining the variance trend in schedule data by comparing the first variance to the second variance, and automatically generating a display representing the variance trend.
19 Citations
12 Claims
-
1. A method for determining a variance trend in schedule data, comprising:
-
retrieving schedule data from a database, the schedule data comprising; a task description of a task; and a plurality of milestones associated with the task, the milestones comprising a baseline milestone associated with a baseline deadline, a first updated milestone associated with a first updated deadline, and a second updated milestone associated with a second updated deadline; calculating, by a processor, a first variance by comparing the first updated deadline to the baseline deadline; calculating, by the processor, a second variance by comparing the second updated deadline to the baseline deadline, the first variance associated with a time prior to that of the second variance; automatically determining, by the processor, the variance trend in schedule data that indicates a change in variance by subtracting the second variance from the first variance, a positive variance trend indicating that the first and second updated deadlines are approaching the baseline deadline; and automatically generating a display representing the variance trend. - View Dependent Claims (2, 3, 4)
-
-
5. A system for determining a variance trend in schedule data, comprising:
-
a records manager comprising a computer processor and operable to retrieve schedule data stored in a database, the schedule data comprising; a task description of a task; and a plurality of milestones associated with the task, the milestones comprising a baseline milestone associated with a baseline deadline, a first updated milestone associated with a first updated deadline, and a second updated milestone associated with a second updated deadline; an analyzer comprising a computer processor and operable to; calculate a first variance by comparing the first updated deadline to the baseline deadline; calculate a second variance by comparing the second updated deadline to the baseline deadline, the first variance associated with a time prior to that of the second variance; and automatically determine the variance trend in schedule data that indicates a change in variance by subtracting the second variance from the first variance, a positive variance trend indicating that the first and second updated deadlines are approaching the baseline deadline; and a display manager operable to automatically generate a display representing the variance trend. - View Dependent Claims (6, 7, 8)
-
-
9. Logic for determining a variance trend in schedule data, the logic embodied in a non-transitory computer readable medium comprising code operable to:
-
retrieve schedule data from a database, the schedule data comprising; a task description of a task; and a plurality of milestones associated with the task, the milestones comprising a baseline milestone associated with a baseline deadline, a first updated milestone associated with a first updated deadline, and a second updated milestone associated with a second updated deadline; and calculate a first variance by comparing the first updated deadline to the baseline deadline; calculate a second variance by comparing the second updated deadline to the baseline deadline, the first variance associated with a time prior to that of the second variance; automatically determine the variance trend in schedule data that indicates a change in variance by subtracting the second variance from the first variance, a positive variance trend indicating that the first and second updated deadlines are approaching the baseline deadline; and automatically generate a display representing the variance trend. - View Dependent Claims (10, 11, 12)
-
Specification