Model based real-time optimization of fuel cell clusters

  • US 7,951,496 B2
  • Filed: 12/18/2007
  • Issued: 05/31/2011
  • Est. Priority Date: 12/20/2006
  • Status: Active Grant
First Claim
Patent Images

1. A power generation system, comprising:

  • a fuel cell controller;

    at least one fuel cell cluster operably connected to the fuel cell controller;

    a data server operably connected to the fuel cell cluster, wherein the data server is configured to obtain operational data from the fuel cell cluster; and

    a model server operably connected to the data server, configured to model operational characteristics of the fuel cell cluster during the actual operation of the fuel cell cluster and modify the operation of the fuel cell cluster in real-time, based on the operational data obtained by the data server.

View all claims