Method for forming monitored concrete pilings using a pour diverter
First Claim
1. A method for casting a piling comprising:
- positioning a plurality of pile strands in a form;
connecting a suspension assembly having a sensor that is at least one of an accelerometer or a strain gauge to at least one of the pile strands so that the at least one sensor is located in a piling core area;
positioning a pour diverter over the suspension assembly;
pouring concrete over the pour diverter, which shields the suspension assembly from a direct flow of the concrete, and into the form; and
removing the pour diverter.
2 Assignments
0 Petitions
Accused Products
Abstract
A method for casting monitored pilings and a pour diverter used in connection with the method is provided. The method includes positioning a plurality of pile strands in a form, and then connecting a suspension assembly having at least one sensor to at least one of the pile strands so that the at least one sensor is located in a piling core area. A pour diverter, having a generally V-shaped configuration, is positioned over the suspension assembly. Concrete is poured into the form over the pour diverter so that a flow of the concrete into the form is split and flows down on either side of the suspension assembly until the at least one sensor is covered. The pour diverter is then removed to finish the casting. Preferably, provisions are provided on the pour diverter for holding or covering an antenna assembly during the pour, prior to it being placed into the concrete forming the piling.
21 Citations
11 Claims
-
1. A method for casting a piling comprising:
-
positioning a plurality of pile strands in a form; connecting a suspension assembly having a sensor that is at least one of an accelerometer or a strain gauge to at least one of the pile strands so that the at least one sensor is located in a piling core area; positioning a pour diverter over the suspension assembly; pouring concrete over the pour diverter, which shields the suspension assembly from a direct flow of the concrete, and into the form; and removing the pour diverter. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8)
-
-
9. A method for casting a piling comprising:
-
positioning a plurality of pile strands in a form; connecting a suspension assembly having a sensor that is at least one of an accelerometer or a strain gauge to at least one of the pile strands so that the at least one sensor is located in a piling core area; positioning a pour diverter over the suspension assembly; connecting an antenna assembly to the one or more sensors; connecting the antenna assembly to or covering the antenna assembly with the pour diverter above a level of the concrete to be poured; pouring concrete into the form; removing the pour diverter; and after the concrete is poured and the diverter is removed, positioning the antenna assembly in the form so that the antenna assembly is generally flush with a surface of the piling. - View Dependent Claims (10, 11)
-
Specification