Performance-based haulage management system
First Claim
1. A computer-implemented method for managing haul routes in work environments, comprising:
- collecting, at a processor associated with a computer, performance data associated with a machine during a haul route run in a work environment;
monitoring, by the processor, a route completion time associated with the machine;
comparing, by the processor, the route completion time with a threshold completion time;
selecting, by the processor, a first payload level for the machine if the route completion time exceeds the threshold completion time;
simulating, by the processor, operation of the machine based on the first payload level to generate a simulated route completion time of the machine; and
establishing, by the processor, a payload limit of the machine as the first payload level if the simulated route completion time does not exceed the threshold completion time.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for managing haul routes in work environments comprises collecting performance data associated with a machine operating in a work environment. The method also includes determining a drive axle torque of the machine and estimating a total effective grade associated with the machine based on the drive axle torque. The estimated total effective grade is compared with a threshold level and, if the estimated total effective grade exceeds the threshold level, a design performance of the machine may be simulated based on the calculated total effective grade. Design performance data is compared with the collected performance data, and a payload limit of the machine is adjusted if the design performance is inconsistent with collected performance data.
-
Citations
16 Claims
-
1. A computer-implemented method for managing haul routes in work environments, comprising:
-
collecting, at a processor associated with a computer, performance data associated with a machine during a haul route run in a work environment; monitoring, by the processor, a route completion time associated with the machine; comparing, by the processor, the route completion time with a threshold completion time; selecting, by the processor, a first payload level for the machine if the route completion time exceeds the threshold completion time; simulating, by the processor, operation of the machine based on the first payload level to generate a simulated route completion time of the machine; and establishing, by the processor, a payload limit of the machine as the first payload level if the simulated route completion time does not exceed the threshold completion time. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A computer-implemented method for managing haul routes in work environments, comprising:
-
collecting, at a processor associated with a computer, performance data associated with a machine operating in a work environment; determining, by the processor, a drive axle torque of the machine and calculating a total effective grade associated with the machine based on the drive axle torque; comparing, by the processor, calculated total effective grade with a threshold level; simulating, by the processor, a design performance of the machine based on the calculated total effective grade if the calculated total effective grade exceeds the threshold level; comparing, by the processor, design performance data with the collected performance data; and adjusting, by the processor, a payload limit of the machine if the design performance is inconsistent with collected performance data. - View Dependent Claims (8, 9, 10, 11, 12, 13, 14, 15, 16)
-
Specification