Method and apparatus for estimation of component gating and shortage risk in manufacturing operations
First Claim
Patent Images
1. A computer-implemented method performed by a computer for identifying a gating component for a plurality of different products estimated to be produced by a manufacturing facility during a planning period, the method comprising:
- providing a connect rate for each component of each product, the connect rate of a component of a product representing the number of the component needed to manufacture one unit of the product;
determining an expected demand for each of the plurality of products;
for each component of the products,determining a quantity that is a maximum availability of the component;
computing, by the computer, a derivative of an expected quantity of the products with respect to a quantity of the component of the products, the expected quantity of the products being a mean production of the products given the quantity of the components and the expected demand for the products;
computing, by the computer, a component gating risk for the component based on the derivative and the connect rate of the component, the component gating risk being the risk that the component will be the cause of a failure to fulfill an order;
determining, by the computer, whether the component is a gating component based on the component gating risk for the component; and
storing an indication of the determined gating component in a memory; and
for each gating component, determining a quantity of the gating component to purchase for availability during the planning period based of the computed gating risk forthe gating component to reduce the probability of the gating component will be the cause of a failure to fulfill an order.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for estimation of component gating risk in manufacturing operations is disclosed. The method includes generating an altered component plan by altering a component plan for a component, computing a mean production value using the altered component plan, and computing the component gating risk using the mean production value.
-
Citations
12 Claims
-
1. A computer-implemented method performed by a computer for identifying a gating component for a plurality of different products estimated to be produced by a manufacturing facility during a planning period, the method comprising:
-
providing a connect rate for each component of each product, the connect rate of a component of a product representing the number of the component needed to manufacture one unit of the product; determining an expected demand for each of the plurality of products; for each component of the products, determining a quantity that is a maximum availability of the component; computing, by the computer, a derivative of an expected quantity of the products with respect to a quantity of the component of the products, the expected quantity of the products being a mean production of the products given the quantity of the components and the expected demand for the products; computing, by the computer, a component gating risk for the component based on the derivative and the connect rate of the component, the component gating risk being the risk that the component will be the cause of a failure to fulfill an order; determining, by the computer, whether the component is a gating component based on the component gating risk for the component; and storing an indication of the determined gating component in a memory; and for each gating component, determining a quantity of the gating component to purchase for availability during the planning period based of the computed gating risk for the gating component to reduce the probability of the gating component will be the cause of a failure to fulfill an order. - View Dependent Claims (2, 3, 4)
-
-
5. A computer-readable storage medium encoded with instructions executable by a processor to identify a gating component for a plurality of different products estimated to be produced by a manufacturing facility during a planning period, by performing acts comprising:
-
providing a connect rate for each component of each product, the connect rate of a component of a product representing the number of the component needed to manufacture one unit of the product; determining an expected demand for each of the plurality of products; for each component of each of the products, determining a quantity that is a maximum availability of the component; computing, by the computer, a derivative of an expected quantity of the products with respect to a quantity of the component of the products, the expected quantity of the products being a mean production of the products given the quantity of the components and the expected demand for the products; computing, by the computer, a component gating risk for the component based on the derivative and the connect rate of the component, the component gating risk being the risk that the component will be the cause of a failure to fulfill an order; determining, by the computer, whether the component is a gating component based on the component gating risk for the component; and storing an indication of the determined gating component in a memory; and for each gating component, reporting to a user the gating risk for the component for use in determining a quantity of the gating component to purchase for availability during the planning period. - View Dependent Claims (6, 7, 8)
-
-
9. A computer system for identifying a gating component for a plurality of different products estimated to be produced by a manufacturing facility during a planning period, the computer system comprising:
-
a memory; and a processor configured to operate on instructions stored in the memory to access a connect rate for each component of each product, the connect rate of a component of a product representing the number of the component needed to manufacture one unit of the product; determine an expected demand for each of the plurality of products; for each component of each of the products, determine a quantity that is a maximum availability of the component; compute a derivative of an expected quantity of the products with respect to a quantity of the component of the products, the expected quantity of the products being a mean production of the products given the quantity of the components and the expected demand for the products; compute a component gating risk for the component based on the derivative and the connect rate of the component, the component gating risk being the risk that the component will be the cause of a failure to fulfill an order; determine whether the component is a gating component based on the component gating risk for the component; and store an indication of the determined gating component in the memory; and for each component, determine a quantity of the gating component to purchase for availability during the planning period factoring in whether the component is a gating component. - View Dependent Claims (10, 11, 12)
-