System, method and apparatus for a modular production tree assembly to reduce weight during transfer of tree to rig

  • US 8,151,890 B2
  • Filed: 10/27/2008
  • Issued: 04/10/2012
  • Est. Priority Date: 10/27/2008
  • Status: Active Grant
First Claim
Patent Images

1. A method of deploying a production tree to a sea floor, comprising:

  • (a) providing an upper tree module, a lower tree module, and a choke bridge module;

    (b) assembling the upper tree module, the lower tree module, and the choke bridge module into operative engagement with each other on land to form a modular production tree assembly and testing the modular production tree assembly;

    (c) after testing the modular production tree assembly, transporting the upper tree module, the lower tree module, and the choke bridge module to an offshore rig;

    (d) separately lifting the upper tree module, the lower tree module, and the choke bridge module onto the offshore rig with a first crane mounted to the offshore rig;

    (e) reassembling on the offshore rig the upper tree module, lower tree module and choke bridge module into the modular production tree assembly;

    then(f) performing interface testing of the modular production tree assembly of interfaces between the upper tree module, lower tree module and choke bridge module; and

    then(g) deploying the modular production tree assembly to the sea floor with a second crane mounted to the offshore rig.