1. A method for implementing a project for a customer, said method comprising:
- developing business requirements of the project, including reviewing the business requirements for acceptability in accordance with business requirements review (BRR) exit criteria;
developing system requirements of the project after the step of developing business requirements, including reviewing the system requirements for acceptability in accordance with system requirements review (SRR) exit criteria, said business requirements being decomposed into the system requirements;
developing component requirements of the project after the step of developing system requirements, including reviewing the component requirements (CR) for acceptability in accordance with component requirements review (PDR) exit criteria, said system requirements being decomposed into the component requirements;
developing component designs compatible with the component requirements anddeveloping test plans for testing the component designs after the step of developing component requirements, including reviewing the component designs and test plans for acceptability in accordance with critical design review (CDR) exit criteria, said component requirements being decomposed into the component designs and the test plans;
a processor of a computer system generating a computer readable Rrequirements Traceability and Verification Matrix (RTVM);
said processor storing the RTVM in a computer readable storage device;
providing the RTVM as input to each of the BRR, SRR, and PDR, said RTVM depicting hierarchical relationships between the business requirements and the system requirements, said RTVM further depicting hierarchical relationships between the system requirements and the component requirements;
updating the RTVM with verification information relating to the business requirements, after the BRR exit criteria have been determined to be satisfied and before the step of developing system requirements has been initiated;
updating the RTVM with verification information relating to the system requirements, after the SRR exit criteria have been determined to be satisfied and before the step of developing component requirements has been initiated;
updating the RTVM with verification information relating to the component requirements, after the PDR exit criteria have been determined to be satisfied and before the steps of developing component designs and developing test plans have been initiated; and
updating the RTVM with verification information relating to the component designs and test plans, after the CDR exit criteria have been determined to be satisfied.
0 Assignments
0 Petitions
Accused Products
Abstract
A method for implementing a project for a customer. Business requirements are developed for the project and are reviewed for acceptability in accordance with Business Requirements Review (BRR) exit criteria. System requirements are developed for the project and are reviewed for acceptability in accordance with system requirements review (SRR) exit criteria. Component requirements are developed for the project and are reviewed for acceptability in accordance with Preliminary Design Review (PDR) exit criteria. The business requirements are decomposed into the system requirements. The system requirements are decomposed into the component requirements. A Requirements Traceability and Verification Matrix (RTVM) is generated when the business requirements are established. The RTVM is updated throughout the life of the project. The RTVM includes verification information relating to the business requirements, the system requirements, and the component requirements. The RTVM depicts hierarchical relationships between the business requirements, the system requirements, and the component requirements.
-
Citations
18 Claims
-
1. A method for implementing a project for a customer, said method comprising:
-
developing business requirements of the project, including reviewing the business requirements for acceptability in accordance with business requirements review (BRR) exit criteria; developing system requirements of the project after the step of developing business requirements, including reviewing the system requirements for acceptability in accordance with system requirements review (SRR) exit criteria, said business requirements being decomposed into the system requirements; developing component requirements of the project after the step of developing system requirements, including reviewing the component requirements (CR) for acceptability in accordance with component requirements review (PDR) exit criteria, said system requirements being decomposed into the component requirements; developing component designs compatible with the component requirements and developing test plans for testing the component designs after the step of developing component requirements, including reviewing the component designs and test plans for acceptability in accordance with critical design review (CDR) exit criteria, said component requirements being decomposed into the component designs and the test plans; a processor of a computer system generating a computer readable Rrequirements Traceability and Verification Matrix (RTVM); said processor storing the RTVM in a computer readable storage device; providing the RTVM as input to each of the BRR, SRR, and PDR, said RTVM depicting hierarchical relationships between the business requirements and the system requirements, said RTVM further depicting hierarchical relationships between the system requirements and the component requirements; updating the RTVM with verification information relating to the business requirements, after the BRR exit criteria have been determined to be satisfied and before the step of developing system requirements has been initiated; updating the RTVM with verification information relating to the system requirements, after the SRR exit criteria have been determined to be satisfied and before the step of developing component requirements has been initiated; updating the RTVM with verification information relating to the component requirements, after the PDR exit criteria have been determined to be satisfied and before the steps of developing component designs and developing test plans have been initiated; and updating the RTVM with verification information relating to the component designs and test plans, after the CDR exit criteria have been determined to be satisfied. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A computer program product, comprising a computer readable storage medium having a computer readable program code stored therein, said computer readable program code configured to be executed by a processor of a computer system to implement a method for implementing a project for a customer, said method comprising:
-
developing business requirements of the project, including reviewing the business requirements for acceptability in accordance with business requirements review (BRR) exit criteria; developing system requirements of the project after the step of developing business requirements, including reviewing the system requirements for acceptability in accordance with system requirements review (SRR) exit criteria, said business requirements being decomposed into the system requirements; and developing component requirements of the project after the step of developing system requirements, including reviewing the component requirements for acceptability in accordance with component requirements review (PDR) exit criteria, said system requirements being decomposed into the component requirements; developing component designs compatible with the component requirements; developing test plans for testing the component designs, said steps of developing component designs and developing test plans including reviewing the component designs and test plans for acceptability in accordance with critical design review (CDR) exit criteria, said component requirements being decomposed into the component designs and the test plans, generating a computer readable Rrequirements Traceability and Verification Matrix (RTVM); and storing the RTVM in a computer readable storage device, said RTVM comprising verification information relating to the business requirements if the BRR exit criteria have been satisfied, said RTVM comprising verification information relating to the system requirements if the SRR exit criteria have been satisfied, said RTVM comprising verification information relating to the component requirements if the PDR exit criteria have been satisfied, said RTVM depicting hierarchical relationships between the business requirements and the system requirements, said RTVM further depicting hierarchical relationships between the system requirements and the component requirements. - View Dependent Claims (8, 9, 10, 11, 12)
-
-
13. A computer system comprising a processor and a computer readable memory unit coupled to the processor, said memory unit containing computer readable program code configured to be executed by the processor to implement a method for implementing a project for a customer, said method comprising:
-
developing business requirements of the project, including reviewing the business requirements for acceptability in accordance with business requirements review (BRR) exit criteria; developing system requirements of the project after the step of developing business requirements, including reviewing the system requirements for acceptability in accordance with system requirements review (SRR) exit criteria, said business requirements being decomposed into the system requirements; and developing component requirements of the project after the step of developing system requirements, including reviewing the component requirements for acceptability in accordance with component requirements review (PDR) exit criteria, said system requirements being decomposed into the component requirements; developing component designs compatible with the component requirements; developing test plans for testing the component designs, said steps of developing component designs and developing test plans including reviewing the component designs and test plans for acceptability in accordance with critical design review (CDR) exit criteria, said component requirements being decomposed into the component designs and the test plans, generating a computer readable Rrequirements Traceability and Verification Matrix (RTVM); and storing the RTVM in a computer readable storage device, said RTVM comprising verification information relating to the business requirements if the BRR exit criteria have been satisfied, said RTVM comprising verification information relating to the system requirements if the SRR exit criteria have been satisfied, said RTVM comprising verification information relating to the component requirements if the PDR exit criteria have been satisfied, said RTVM depicting hierarchical relationships between the business requirements and the system requirements, said RTVM further depicting hierarchical relationships between the system requirements and the component requirements. - View Dependent Claims (14, 15, 16, 17, 18)
-
Specification