1. A computer implemented method for management of materials on a construction site, said method comprising:

  • defining at least one cost scenario to move at least one material with at least one vehicle from a vehicle pool;

    determining a status of a project which uses the at least one material;

    generating a report which identifies a vehicle from said vehicle pool to be utilized and defines a load of the material which is to be moved by said vehicle, according to a mass haul plan, from a first location which is a cut section to a second location which is a fill section;

    automatically updating the status of the project based on an actual size and an actual drop-off location of the load of the material moved by said vehicle; and

    updating the report based on the updating of the status of the project.