Resource management tool
First Claim
1. A device to manage resources for performing operations in a computer system, the device comprising:
- a resource reservation unit to reserve resources for performing an operation specified by a user;
a query unit to query the user regarding reserving additional resources in the event the operation cannot be completed within a reserved time using the reserved resources;
a resumption instruction unit to cause the resource reservation unit to reserve the additional resources and continue the operation at an agreed-upon resumption fee upon receiving a resumption instruction from the user in response to the query; and
the resumption instruction unit further configured to, prior to receiving the resumption instruction from the user, cause the resource reservation unit to reserve free resources and resume the operation, wherein the resumption instruction unit charges a modified resumption fee in the event the operation is resumed prior to receiving the resumption instruction.
2 Assignments
0 Petitions
Accused Products
Abstract
A device, computer program product, and method for managing resources for performing operations in a computer system are presented. The device may include a resource reservation unit to reserve resources for performing an operation specified by a user. A query unit may query the user whether to reserve additional resources in the event the operation cannot be completed within a reserved time in the reserved resources. A resumption instruction unit may cause the resource reservation unit to reserve the additional resources and cause a continuation of the operation in the additional resources upon receiving a resumption instruction in response to the query.
-
Citations
17 Claims
-
1. A device to manage resources for performing operations in a computer system, the device comprising:
-
a resource reservation unit to reserve resources for performing an operation specified by a user; a query unit to query the user regarding reserving additional resources in the event the operation cannot be completed within a reserved time using the reserved resources; a resumption instruction unit to cause the resource reservation unit to reserve the additional resources and continue the operation at an agreed-upon resumption fee upon receiving a resumption instruction from the user in response to the query; and the resumption instruction unit further configured to, prior to receiving the resumption instruction from the user, cause the resource reservation unit to reserve free resources and resume the operation, wherein the resumption instruction unit charges a modified resumption fee in the event the operation is resumed prior to receiving the resumption instruction. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10)
-
-
11. A computer program product to manage resources for performing operations in a computer system, the computer program product comprising:
a non-transitory computer-readable medium having computer usable program code stored therein, the computer-usable program code comprising; computer-usable program code to reserve resources for performing an operation specified by a user; computer-usable program code to query the user regarding whether to reserve additional resources in the event the operation cannot be completed within a reserved time using the reserved resources; computer-usable program code to reserve the additional resources and cause a continuation of the operation at an agreed-upon resumption fee upon receiving a resumption instruction from the user to reserve the additional resources; and computer-usable program code to, prior to receiving the resumption instruction from the user, reserve free resources and resume the operation at a modified resumption fee. - View Dependent Claims (12, 13, 14, 15)
-
16. A method for managing resources performing operations in a computer system, the method comprising:
-
reserving resources for performing an operation specified by a user; querying the user to determine whether to reserve additional resources in the event the operation cannot be completed within a reserved time using the reserved resources; upon receiving a resumption instruction from the user, reserving the additional resources and causing a continuation of the operation at an agreed-upon resumption fee; and prior to receiving the resumption instruction from the user, reserving free resources and resuming the operation at a modified resumption fee. - View Dependent Claims (17)
-
Specification