Load shedding by an electric utility

  • US 8,682,498 B2
  • Filed: 01/07/2012
  • Issued: 03/25/2014
  • Est. Priority Date: 07/07/2009
  • Status: Expired due to Fees
First Claim
Patent Images

1. A method of participating in electric utility load shedding, the electric utility configured to provide electricity to one or more power distribution systems organized into one or more substations, at least one power distribution system in each substation comprising a distributed renewable generation (‘

  • DRG’

    ) system, the DRG system configured to provide power to the electric utility, a local load, and one or more batteries for storage, each power distribution system connected for data communications through a data communications network to the electric utility, the method comprising;

    storing a predetermined threshold in a machine-readable recording media configured to be accessed by a control engine;

    receiving from the electric utility, by the control engine of a power distribution system that includes a DRG system, a query for present power consumption of the local load of the power distribution system, wherein the present power consumption is a present power consumption rate;

    retrieving the predetermined threshold from the machine-readable recording media by the control engine for use in comparing the predetermined threshold with a present state of charge of the one or more batteries;

    determining whether the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold, wherein the predetermined threshold is defined by the present state of charge being sufficient for the one or more batteries to supply the local load of the power distribution system for a blackout of a predefined length of time;

    implementing a policy of the DRG system of responding to the electric utility'"'"'s query with the present power consumption of the local load only if the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold,making a determination that said present state of charge is not greater than the predetermined threshold; and

    ignoring the query by declining to provide the present power consumption of the local load of the power distribution system in response to the determination that said present state of charge is not greater than the predetermined threshold.

View all claims
  • 0 Assignments
Timeline View