Load shedding by an electric utility
First Claim
1. A method of participating in electric utility load shedding, the electric utility configured to provide electricity to one or more power distribution systems organized into one or more substations, at least one power distribution system in each substation comprising a distributed renewable generation (‘
- DRG’
) system, the DRG system configured to provide power to the electric utility, a local load, and one or more batteries for storage, each power distribution system connected for data communications through a data communications network to the electric utility, the method comprising;
storing a predetermined threshold in a machine-readable recording media configured to be accessed by a control engine;
receiving from the electric utility, by the control engine of a power distribution system that includes a DRG system, a query for present power consumption of the local load of the power distribution system, wherein the present power consumption is a present power consumption rate;
retrieving the predetermined threshold from the machine-readable recording media by the control engine for use in comparing the predetermined threshold with a present state of charge of the one or more batteries;
determining whether the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold, wherein the predetermined threshold is defined by the present state of charge being sufficient for the one or more batteries to supply the local load of the power distribution system for a blackout of a predefined length of time;
implementing a policy of the DRG system of responding to the electric utility'"'"'s query with the present power consumption of the local load only if the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold,making a determination that said present state of charge is not greater than the predetermined threshold; and
ignoring the query by declining to provide the present power consumption of the local load of the power distribution system in response to the determination that said present state of charge is not greater than the predetermined threshold.
0 Assignments
0 Petitions
Accused Products
Abstract
Load shedding by an electric utility, including querying power distribution systems that include a DRG system for present power consumption of the local load of the power distribution system; selecting, in dependence upon the present power consumption of the local load of the power distribution systems and predefined power consumption criteria for each substation, a substation to receive a reduction in power; and reducing power provided to the selected substation.
58 Citations
8 Claims
-
1. A method of participating in electric utility load shedding, the electric utility configured to provide electricity to one or more power distribution systems organized into one or more substations, at least one power distribution system in each substation comprising a distributed renewable generation (‘
- DRG’
) system, the DRG system configured to provide power to the electric utility, a local load, and one or more batteries for storage, each power distribution system connected for data communications through a data communications network to the electric utility, the method comprising;storing a predetermined threshold in a machine-readable recording media configured to be accessed by a control engine; receiving from the electric utility, by the control engine of a power distribution system that includes a DRG system, a query for present power consumption of the local load of the power distribution system, wherein the present power consumption is a present power consumption rate; retrieving the predetermined threshold from the machine-readable recording media by the control engine for use in comparing the predetermined threshold with a present state of charge of the one or more batteries; determining whether the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold, wherein the predetermined threshold is defined by the present state of charge being sufficient for the one or more batteries to supply the local load of the power distribution system for a blackout of a predefined length of time; implementing a policy of the DRG system of responding to the electric utility'"'"'s query with the present power consumption of the local load only if the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold, making a determination that said present state of charge is not greater than the predetermined threshold; and ignoring the query by declining to provide the present power consumption of the local load of the power distribution system in response to the determination that said present state of charge is not greater than the predetermined threshold. - View Dependent Claims (2, 3, 4)
- DRG’
-
5. An apparatus for participating in electric utility load shedding, the electric utility configured to provide electricity to one or more power distribution systems organized into one or more substations, at least one power distribution system in each substation comprising a distributed renewable generation (‘
- DRG’
) system, the DRG system configured to provide power to the electric utility, a local load, and one or more batteries for storage, each power distribution system connected for data communications through a data communications network to the electric utility, the apparatus comprising a computer processor, a non-transitory computer memory operatively coupled to the computer processor, the computer memory having disposed within it computer program instructions configured for;storing a predetermined threshold in a machine-readable recording media configured to be accessed by a control engine; and receiving from the electric utility, by the control engine of a power distribution system that includes a DRG system, a query for present power consumption of the local load of the power distribution system, wherein the present power consumption is a present power consumption rate; retrieving the predetermined threshold from the machine-readable recording media by the control engine for use in comparing the predetermined threshold with a present state of charge of the one or more batteries; determining whether the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold, wherein the predetermined threshold is defined by the present state of charge being sufficient for the one or more batteries to supply the local load of the power distribution system for a blackout of a predefined length of time; implementing a policy of the DRG system of responding to the electric utility'"'"'s query with the present power consumption of the local load only if the present state of charge of the one or more batteries of the power distribution system is greater than the predetermined threshold; making a determination that said present state of charge is not greater than the predetermined threshold; and ignoring the query by declining to provide the present power consumption of the local load of the power distribution system in response to the determination that said present state of charge is not greater than the predetermined threshold. - View Dependent Claims (6, 7, 8)
- DRG’
Specification