Method of estimating the maximum power generation capacity and for controlling a specified power reserve of a single cycle or combined cycle gas turbine power plant, and a power generating system for use with said method

  • US 8,700,223 B2
  • Filed: 11/21/2012
  • Issued: 04/15/2014
  • Est. Priority Date: 06/26/2008
  • Status: Expired due to Fees
First Claim
Patent Images

1. A method for controlling a specified power reserve of a gas turbine power plant having an input means which generates a load set-point signal for the gas turbine power plant and a controller which receives the load set-point signal and regulates a power output of the gas turbine power plant, the method comprising:

  • arranging a processor coupled to a memory to;

    continuously update an estimate of the maximum power generation capacity of the gas turbine power plant;

    calculate a load offset by specifying a power reserve and determining the load offset from the specified power reserve;

    calculate a load limit as a difference of the estimate of the maximum power generation capacity and the load offset; and

    apply the load limit as an upper limit of the load set-point signal to obtain a limited load set-point signal.

View all claims
  • 2 Assignments
Timeline View