Dynamic load curtailment system and method
First Claim
1. A method of load curtailment for a facility, comprising:
- examining a number of previous days of metering information to identify a demand peak target, wherein the examining step comprisescalculating a target total facility KW value such that the target total facility KW is the greater of;
a first proportion times recent total facility demand peak, where recent total facility demand peak is equal to the highest total facility demand value for the number of previous days, anda second proportion times recent occupied average total facility load, where recent occupied average total facility load is equal to the average value of total facility load during occupied hours for the number of previous days;
utilizing real-time load information to predict the demand peak of the upcoming interval; and
,strategically curtailing assigned loads in order to limit the demand peak so as not to set a new peak;
whereby an automated tuning operation is created and the building operates with improved efficiency.
4 Assignments
0 Petitions
Accused Products
Abstract
A system that dynamically learns the optimum energy consumption operating condition for a building and monitors/controls energy consuming equipment to keep the peak demand interval at a minimum. The algorithm employs two separate control schemes, one for HVAC loads and one for non-HVAC loads, and uses historical peak demand measurements in its real-time limiting strategy. The algorithm continuously attempts to reduce peak demand within user configured parameters. When a new peak is inevitable, the algorithm removes and/or introduces loads to limit the new peak magnitude and places the operating conditions within the user configured parameters. The algorithm can examine the previous seven days of metering information to identify a peak demand interval, use real-time load information to predict the demand peak of the upcoming interval, and curtail loads in order to limit the demand peak so as not to set a new peak.
15 Citations
7 Claims
-
1. A method of load curtailment for a facility, comprising:
-
examining a number of previous days of metering information to identify a demand peak target, wherein the examining step comprises calculating a target total facility KW value such that the target total facility KW is the greater of; a first proportion times recent total facility demand peak, where recent total facility demand peak is equal to the highest total facility demand value for the number of previous days, and a second proportion times recent occupied average total facility load, where recent occupied average total facility load is equal to the average value of total facility load during occupied hours for the number of previous days; utilizing real-time load information to predict the demand peak of the upcoming interval; and
,strategically curtailing assigned loads in order to limit the demand peak so as not to set a new peak; whereby an automated tuning operation is created and the building operates with improved efficiency. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. Computer program process code, tangibly stored on at least one non-transitory computer readable medium, the computer program process code comprising instructions implementing a method for using a computing device to perform dynamic load curtailment, comprising instructions for:
-
examining a number of previous days of metering information to identify a demand peak target, wherein the examining step comprises calculating a target total facility KW value such that the target total facility KW is the greater of; a first proportion times recent total facility demand peak, where recent total facility demand peak is equal to the highest total facility demand value for the number of previous days, and a second proportion times recent occupied average total facility load, where recent occupied average total facility load is equal to the average value of total facility load during occupied hours for the number of previous days; utilizing real-time load information to predict the demand peak of the upcoming interval; and
,strategically curtailing assigned loads in order to limit the demand peak so as not to set a new peak; whereby an automated tuning operation is created and the building operates with improved efficiency.
-
Specification