Triple activity drilling ship
First Claim
Patent Images
1. A method comprising:
- running a marine riser and blowout preventer from a first station of a ship into the sea;
running a conductor from a second station on the ship into the sea while the marine riser and blowout preventer are being run; and
refraining from running said marine riser and blowout preventer when said conductor is in contact with the seabed.
1 Assignment
0 Petitions
Accused Products
Abstract
A triple activity drilling ship may be provided with two separate drilling centers, each including drilling apparatus. In addition, a trolley that is capable of supporting tubulars may be positioned between a first position within one of said drilling centers and a second position outside that drilling center. As a result, the trolley may be used to hold assembled tubulars while other activities are ongoing in one or more of the drilling centers.
27 Citations
9 Claims
-
1. A method comprising:
-
running a marine riser and blowout preventer from a first station of a ship into the sea; running a conductor from a second station on the ship into the sea while the marine riser and blowout preventer are being run; and refraining from running said marine riser and blowout preventer when said conductor is in contact with the seabed. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
Specification