Power management system
First Claim
1. A power management system, comprising:
- a power system;
a powered component coupled to the power system;
a power detect circuit coupled to the power system; and
a power system controller coupled to the power system, the powered component, and the power detect circuit, wherein the power system controller is configured, for each of at least one workload run using the powered component, to;
program the power detect circuit with a first threshold for a first system operation setting;
determine that the first threshold for the first system operation setting was not exceeded during the running of a first workload of the at least one workload and, in response to the first threshold for the first system operation setting not being exceeded during the running of the first workload, program the power detect circuit with a second threshold for the first system operation setting that is less than the first threshold for the first system operation setting; and
determine that the second threshold for the first system operation setting was exceeded during the running of the first workload and, in response, use the second threshold for the first system operation setting to allocate power from the power system.
14 Assignments
0 Petitions
Accused Products
Abstract
A power management system includes a power system. A powered component is coupled to the power system. A power detect circuit is coupled to the power system. A power system controller is coupled to the power system, the powered component, and the power detect circuit. The power system controller is operable, for each of at least one workload run using the powered component, to program the power detect circuit with a first threshold for a first system operation setting and determine that the first threshold was not exceeded while the workload was running. The power system controller is then operable to program the power detect circuit with a second threshold for the first system operation setting, determine that the second threshold was exceeded while the workload was running and, in response, use the second threshold to allocate power from the power system.
-
Citations
20 Claims
-
1. A power management system, comprising:
-
a power system; a powered component coupled to the power system; a power detect circuit coupled to the power system; and a power system controller coupled to the power system, the powered component, and the power detect circuit, wherein the power system controller is configured, for each of at least one workload run using the powered component, to; program the power detect circuit with a first threshold for a first system operation setting; determine that the first threshold for the first system operation setting was not exceeded during the running of a first workload of the at least one workload and, in response to the first threshold for the first system operation setting not being exceeded during the running of the first workload, program the power detect circuit with a second threshold for the first system operation setting that is less than the first threshold for the first system operation setting; and determine that the second threshold for the first system operation setting was exceeded during the running of the first workload and, in response, use the second threshold for the first system operation setting to allocate power from the power system. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. An information handling system (IHS), comprising:
-
a processor; a power detect circuit coupled to the processor; and a power system controller coupled to the processor and the power detect circuit, wherein the power system controller is configured to couple to a power system and, for each of at least one workload run using the processor, to; program the power detect circuit with a first threshold for a first system operation setting; determine that the first threshold for the first system operation setting was not exceeded during the running of a first workload of the at least one workload and, in response to the first threshold for the first system operation setting not being exceeded during the running of the first workload, program the power detect circuit with a second threshold for the first system operation setting that is less than the first threshold for the first system operation setting; and determine that the second threshold for the first system operation setting was exceeded during the running of the first workload and, in response, use the second threshold for the first system operation setting to allocate power from the power system. - View Dependent Claims (9, 10, 11, 12, 13, 14)
-
-
15. A method for managing power, comprising:
-
running at least one workload using a powered component; programming a power detect circuit with a first threshold for a first system operation setting; determining that the first threshold for the first system operation setting was not exceeded while a first workload of the at least one workload was run using the powered component and, in response to the first threshold for the first system operation setting not being exceeded while the first workload was run, programming the power detect circuit with a second threshold for the first system operation setting that is less than the first threshold for the first system operation setting; and determining that the second threshold for the first system operation setting was exceeded while the first workload was run using the powered component and, in response, using the second threshold for the first system operation setting to allocate power from a power system. - View Dependent Claims (16, 17, 18, 19, 20)
-