1. A system, comprising:

  • a processor, coupled to a memory, that executes or facilitates execution of executable components, comprising;

    an analyzer component configured to perform an analysis of information relating to power conditions associated with multi-phase power being distributed to one or more consumer consumption nodes (CCNs) to enable identification of at least a phase imbalance in the multi-phase power between at least a first phase associated with a first power transmission line and a second phase associated with a second power transmission line that distribute respective portions of the multi-phase power to the one or more CCNs in response to occurrence of at least the phase imbalance, wherein the one or more CCNs are located in a portion of a tier in a multi-tier electrical distribution network (EDN) lower than at least one other tier of the multi-tier EDN; and

    a first power control component configured to identify the phase imbalance and control distribution of the multi-phase power in the portion of the tier via at least one junction node based at least in part on the analysis of at least a set of the information relating to the portion of the tier, in accordance with at least one defined control criterion, to control an amount of the phase imbalance in the multi-phase power in the portion of the tier by at least switching an electrical connection of a CCN of the one or more CCNs from the first power transmission line associated with the first phase to the second transmission line associated with the second phase to mitigate the amount of the phase imbalance in the multi-phase power in the portion of the tier,wherein the at least one defined control criterion comprises at least one defined power distribution criterion that relates to at least one of a maximization of a net consumption of the multi-phase power at the tier, a minimization of requests or demands for the multi-phase power to be transferred from a higher tier in a hierarchy of the multi-tier EDN to the tier, a minimization of the phase imbalance in the multi-phase power, a minimization of a harmonic level in the multi-phase power, a minimization of an interference in the multi-phase power, a type of load connected to the multi-phase power, a number of tiers in the multi-tier EDN, a respective number of power control components or node controller components in respective tiers of the multi-tier EDN, a maximum amount of the multi-phase power that is receivable by a power distribution source (PDS) at a given time, a maximum amount of the multi-phase power that is distributable at the given time by the PDS, a maximum operating temperature of the PDS, power distribution control information or rules received from the higher tier in the multi-tier EDN, available local power from local power distribution sources in the tier, expected or predicted future power demands in the tier, or consumer agreements relating to the distribution of the multi-phase power for the one or more CCNs in the tier.