Electrical transfer capacity optimization systems and methods thereof
First Claim
1. An electric capacity rating system for determining the quantity of electrical energy that can flow through electric power facilities for a given time period and at any given point in time, comprising:
- a processor for receiving and storing information about the capability of resources to transfer electric power in one or more electric power facilities;
a capability datastore in communication with said processor for determining electrical transfer capabilities of each resource in the one or more electric power facilities for a given time period and at any given point in time, wherein the resources include;
overhead line conductors, underground cables, conductor splices, conductor compression terminals, buses, disconnects, wave traps, current limiting reactors, circuit breakers, circuit switches, current transformers, series capacitors, shunt capacitors, substations and relays;
an external factors datastore for determining a plurality of variables which affect said electrical transfer capabilities of electric power facilities; and
a resource manager for allocating said plurality of resources by optimizing said electrical transfer capabilities of electric power facilities for a given time period and at any given point in time based on said plurality of variables;
said resource manager correlating said plurality of variables with said electrical transfer capabilities of each resource to compute an overall electric transfer capacity rating for a given time period and at a given point in time for said one or more electric power facilities, wherein the overall electric transfer capacity rating indicates the quantity of electrical energy that can flow through said one or more electric power facilities; and
said resource manager, said external factors datastore, and said capability datastore being in processing communication with said processor and with each other.
0 Assignments
0 Petitions
Accused Products
Abstract
A method and system is provided for determining and optimizing electric transfer capacities of electric power system facilities. A processor receives and stores information that is used to compute the quantity of electric power that can flow through one or more electric power facilities. A capability datastore and an external factors datastore communicate with the processor and with each other. The capability datastore computes and stores the electrical transfer capability as a function time duration and at any given point in time while the external factors datastore determines a plurality of variables which affect the electrical transfer capabilities. A resource manager, connected to the processor, allocates resources by optimizing and correlating the electrical transfer capabilities with the plurality of variables, to generate an electrical transfer capacity rating for the one or more electric power facilities as a function of time duration and at any given point in time.
-
Citations
20 Claims
-
1. An electric capacity rating system for determining the quantity of electrical energy that can flow through electric power facilities for a given time period and at any given point in time, comprising:
-
a processor for receiving and storing information about the capability of resources to transfer electric power in one or more electric power facilities; a capability datastore in communication with said processor for determining electrical transfer capabilities of each resource in the one or more electric power facilities for a given time period and at any given point in time, wherein the resources include;
overhead line conductors, underground cables, conductor splices, conductor compression terminals, buses, disconnects, wave traps, current limiting reactors, circuit breakers, circuit switches, current transformers, series capacitors, shunt capacitors, substations and relays;an external factors datastore for determining a plurality of variables which affect said electrical transfer capabilities of electric power facilities; and a resource manager for allocating said plurality of resources by optimizing said electrical transfer capabilities of electric power facilities for a given time period and at any given point in time based on said plurality of variables; said resource manager correlating said plurality of variables with said electrical transfer capabilities of each resource to compute an overall electric transfer capacity rating for a given time period and at a given point in time for said one or more electric power facilities, wherein the overall electric transfer capacity rating indicates the quantity of electrical energy that can flow through said one or more electric power facilities; and said resource manager, said external factors datastore, and said capability datastore being in processing communication with said processor and with each other. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)
-
-
14. A method for optimizing electric loading transfer capability, comprising:
-
establishing processing communication between a resource manager, an external factors datastore, a capability datastore, and a processor; receiving and storing information about resources in one or more electric power facilities by said processor; determining electrical transfer capabilities of each resource in the one or more electric power facilities for a given time period and at any given point in time using said capability datastore, wherein the resources include;
overhead line conductors, underground cables, conductor splices, conductor compression terminals, buses, disconnects, wave traps, current limiting reactors, circuit breakers, circuit switches, current transformers, series capacitors, shunt capacitors, substations and relays;determining a plurality of variables which affect said electrical transfer capabilities using said external factors datastore; allocating said plurality of resources by using said resource manager to optimize said electrical transfer capabilities for a given time period and at any given point in time based on said plurality of variables; correlating said plurality of variables with said electrical transfer capabilities of each resource to generate an overall electric transfer capacity rating for a given time period and at a given point in time of said one or more electric power facilities by using said resource manager, wherein the overall electric transfer capacity rating indicates the quantity of electrical energy that can flow through said one or more electrical power facilities. - View Dependent Claims (15, 16, 17, 18, 19)
-
-
20. A computer program product comprising an optimized electric loading transfer tool including a non-transitory computer usable medium having computer readable program code means for causing a computer to effect method steps of:
-
establishing processing communication between a resource manager, an external factors datastore, a capability datastore, and a processor; receiving and storing information about resources in one or more electric power facilities by said processor; determining electrical transfer capabilities of each resource in the one or more electric power facilities for a given time period and at any given point in time using said capability datastore, wherein the resources include;
overhead line conductors, underground cables, conductor splices, conductor compression terminals, buses, disconnects, wave traps, current limiting reactors, circuit breakers, circuit switches, current transformers, series capacitors, shunt capacitors, substations and relays;determining a plurality of variables which affect said electrical transfer capabilities using said external factors datastore; allocating said plurality of resources by using said resource manager to optimize said electrical transfer capabilities for a given time period and at any given point in time based on said plurality of variables; correlating said plurality of variables with said electrical transfer capabilities of each resource to generate an overall electric transfer capacity rating for a given time period and at a given point in time of said one or more electric power facilities by using said resource manager;
wherein the overall electric transfer capacity rating indicates the quantity of electrical energy that can flow through said one or more electric power facilities.
-
Specification