Battery management
First Claim
1. In a system having a battery bank which includes a plurality of battery strings, a method for battery management, the method comprising:
- performing a pretest routine on a first battery string in the battery bank, the pretest routine comprising;
measuring a pretest open circuit voltage of each of a plurality of batteries in the first battery string, andin response to the pretest open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage, performing a preliminary charge routine, the preliminary charge routine comprising;
charging each of the batteries in the first battery string which has a pretest open circuit voltage which is below the predetermined voltage for a predetermined time period; and
measuring the pretest open circuit voltage of each of the batteries in the first battery string which were charged in response to having a pretest open circuit voltage which was below the predetermined voltage, until the pretest open circuit voltage of each of the batteries in the first battery string has increased less than a preliminary charge voltage difference;
in response to the pretest open circuit voltage of each of the batteries in the first battery string increasing less than the preliminary charge voltage difference, performing a main charge routine, the main charge routine comprising;
charging select ones of the batteries in the first battery string for a charge time,isolating the select ones of the batteries in the first battery string from charging for a rest time to keep the select ones of the batteries in the first battery string, and each of the batteries in the battery strings of the battery bank, from undergoing continuous charging,repeating the charging of the select ones of the batteries in the first battery string for the charge time and the isolating of the select ones of the batteries in the first battery string from charging for the rest time a predetermined number of times, andmeasuring a post charge open circuit voltage for each of the batteries in the first battery string, until the post charge open circuit voltage of each battery in the first battery string has increased less than a predetermined charging voltage differential corresponding to each battery in the first battery string having a substantially full charge;
performing a non-load testing routine comprising;
measuring a test open circuit voltage for each battery in the first battery string, andin response to the test open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage level, recording, in a database, a first defective indicator for each of the batteries in the first battery string which has a test open circuit voltage which is below the predetermined voltage level, the first defective indicator corresponding to the batteries being defective; and
performing a load testing routine on each of the batteries in the first battery string not having the first defective indicator stored in the database, wherein performing the load testing routine comprises;
loading each of the batteries in the first battery string not having the first defective indicator stored in the database with a preset load for a load time,
measuring, after the load time, a test load voltage for each of the batteries loaded with the preset load, and
in response to a difference between the test open circuit voltage and the test load voltage of any of the batteries loaded with the preset load being greater than a load voltage differential, recording, in the database, a second defective indicator for each of the batteries in the first battery string for which the difference is greater than the load voltage differential, the second defective indicator corresponding to the batteries being defective.
2 Assignments
0 Petitions
Accused Products
Abstract
Battery management may be provided. First, a battery string in a battery bank may be charged for a charge time. After charging the battery string, the battery string may be isolated from charging for a rest time. Once the charging and resting from charging is complete, a test open circuit voltage for each battery in the first battery string may be measured. In addition, a defective indicator that a battery is defective may be recorded in a database. Next, a battery may be loaded with a preset load for a load time. After loading the battery, a test load voltage for each of the batteries loaded with the preset load may be measured. A second defective indicator that a battery is defective may be recorded in the database when the test load voltage for the second battery is greater than a load voltage differential.
25 Citations
14 Claims
-
1. In a system having a battery bank which includes a plurality of battery strings, a method for battery management, the method comprising:
performing a pretest routine on a first battery string in the battery bank, the pretest routine comprising; measuring a pretest open circuit voltage of each of a plurality of batteries in the first battery string, and in response to the pretest open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage, performing a preliminary charge routine, the preliminary charge routine comprising; charging each of the batteries in the first battery string which has a pretest open circuit voltage which is below the predetermined voltage for a predetermined time period; and measuring the pretest open circuit voltage of each of the batteries in the first battery string which were charged in response to having a pretest open circuit voltage which was below the predetermined voltage, until the pretest open circuit voltage of each of the batteries in the first battery string has increased less than a preliminary charge voltage difference; in response to the pretest open circuit voltage of each of the batteries in the first battery string increasing less than the preliminary charge voltage difference, performing a main charge routine, the main charge routine comprising; charging select ones of the batteries in the first battery string for a charge time, isolating the select ones of the batteries in the first battery string from charging for a rest time to keep the select ones of the batteries in the first battery string, and each of the batteries in the battery strings of the battery bank, from undergoing continuous charging, repeating the charging of the select ones of the batteries in the first battery string for the charge time and the isolating of the select ones of the batteries in the first battery string from charging for the rest time a predetermined number of times, and measuring a post charge open circuit voltage for each of the batteries in the first battery string, until the post charge open circuit voltage of each battery in the first battery string has increased less than a predetermined charging voltage differential corresponding to each battery in the first battery string having a substantially full charge; performing a non-load testing routine comprising; measuring a test open circuit voltage for each battery in the first battery string, and in response to the test open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage level, recording, in a database, a first defective indicator for each of the batteries in the first battery string which has a test open circuit voltage which is below the predetermined voltage level, the first defective indicator corresponding to the batteries being defective; and performing a load testing routine on each of the batteries in the first battery string not having the first defective indicator stored in the database, wherein performing the load testing routine comprises;
loading each of the batteries in the first battery string not having the first defective indicator stored in the database with a preset load for a load time,
measuring, after the load time, a test load voltage for each of the batteries loaded with the preset load, and
in response to a difference between the test open circuit voltage and the test load voltage of any of the batteries loaded with the preset load being greater than a load voltage differential, recording, in the database, a second defective indicator for each of the batteries in the first battery string for which the difference is greater than the load voltage differential, the second defective indicator corresponding to the batteries being defective.- View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
10. A system for use with a battery bank which includes a plurality of battery strings, the system comprising:
-
means for performing a pretest routine on a first battery string in the battery bank, the pretest routine comprising; measuring a pretest open circuit voltage of each of a plurality of batteries in the first battery string, and in response to the pretest open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage, performing a preliminary charge routine, the preliminary charge routine comprising; charging each of the batteries in the first battery string which has a pretest open circuit voltage which is below the predetermined voltage for a predetermined time period; and measuring the pretest open circuit voltage of each of the batteries in the first battery string which were charged in response to having a pretest open circuit voltage which was below the predetermined voltage, until the pretest open circuit voltage of each of the batteries in the first battery string has increased less than a preliminary charge voltage difference; means for performing a main charge routine in response to the pretest open circuit voltage of each of the batteries in the first battery string increasing less than the preliminary charge voltage difference, wherein the main charge routine comprises; charging select ones of the batteries in the first battery string for a charge time; isolating the select ones of the batteries in the first battery string from charging for a rest time to keep the select ones of the batteries in the first battery string, and each of the batteries in the battery strings of the battery bank, from undergoing continuous charging; repeating the charging of the select ones of the batteries in the first battery string for the charge time and the isolating of the select ones of the batteries in the first battery string from charging for the rest time a predetermined number of times; and measuring a post charge open circuit voltage for each of the batteries in the first battery string, until the post charge open circuit voltage of each battery in the first battery string has increased less than a predetermined charging voltage differential corresponding to each battery in the first battery string having a substantially full charge; means for performing a non-load testing routine comprising; means for measuring a test open circuit voltage for each battery in the first battery string, and means for recording wherein in response to the test open circuit voltage of any of the batteries in the first battery string being below a predetermined voltage level, said means for recording records, in a database, a first defective indicator for each of the batteries in the first battery string which has a test open circuit voltage which is below the predetermined voltage level, the first defective indicator corresponding to the batteries being defective; and means for performing a load testing routine on each of the batteries in the first battery string not having the first defective indicator stored in the database, wherein the load testing routine comprises; loading each of the batteries in the first battery string not having the first defective indicator stored in the database with a preset load for a load time, measuring, after the load time, a test load voltage for each of the batteries loaded with the preset load, and in response to a difference between the test open circuit voltage and the test load voltage of any of the batteries loaded with the preset load being greater than a load voltage differential, recording, in the database, a second defective indicator for each of the batteries in the first battery string for which the difference is greater than the load voltage differential, the second defective indicator corresponding to the batteries being defective. - View Dependent Claims (11, 12, 13, 14)
-
Specification