Hybrid electric generating power plant that uses a combination of real-time generation facilities and energy storage system

  • US 9,559,520 B2
  • Filed: 06/19/2012
  • Issued: 01/31/2017
  • Est. Priority Date: 06/20/2011
  • Status: Active Grant
First Claim
Patent Images

1. A method of controlling power supplied to an electric grid using at least one energy storage device to store energy, the method comprising:

  • receiving, in a grid indication receiver, an indication of power to be supplied to the electric grid;

    generating power from at least one power generator;

    receiving, by a controller, the received indication of power to be supplied to the grid from the grid indication receiving device;

    determining, by the controller, an optimum discharge and storage profile of the at least one energy storage device or a predetermined power discharge and storage profile of the at least one energy storage device;

    adjusting, by the controller, the storage of energy by the at least one energy storage device according to the optimum discharge and storage profile or the predetermined power discharge and storage profile of the at least one energy storage device; and

    adjusting, based on the optimum or predetermined power discharge and storage profile of the at least one energy storage device, power generation from the at least one power generator to satisfy the indication of power to be supplied to the electric grid received from the grid indication receiver,wherein the indication includes at least one of;

    (1) a signal that indicates a present power supply level to be supplied to the electric grid,(2) a signal indicating a grid frequency for determining a present adjustment to the power to be supplied to the electric grid, or(3) one or more operating parameters indicating one or more operating set points for operation of a combination of the at least one power generator and the energy storage device, andwherein the optimum or the predetermined power discharge and storage profile of the at least one energy storage device and an optimum or a predetermined ramp profile of the at least one power generator are based on at least two factors selected from the group consisting of;

    (1) wear and tear on respective equipment;

    (2) an optimum rate of change of the at least one power generator;

    (3) a fuel consumption rate profile of the at least one power generator;

    (4) a state of charge (SOC) of the at least one energy storage device;

    (5) a durability of the respective equipment,(6) costs of initial acquisition and depreciation of the at least one power generator and the at least one energy storage device; and

    (7) transmission losses of the power distributed by the electric grid.

View all claims
  • 3 Assignments
Timeline View
Assignment View
    ×
    ×