Over-rating control of wind turbines and power plants

  • US 9,599,096 B2
  • Filed: 09/30/2011
  • Issued: 03/21/2017
  • Est. Priority Date: 09/30/2010
  • Status: Active Grant
First Claim
Patent Images

1. A controller for a wind turbine power plant, the wind turbine power plant comprising a plurality of wind turbines, the wind turbine power plant producing an output power and having a rated output power, the controller comprising:

  • a power plant set point control (PPSC) unit configured to schedule, based on received electricity price data, a plurality of set point values for the output power, wherein at least one scheduled set point value corresponds to an output power value greater than the rated output power;

    an optimizer unit configured to determine a plurality of overrating values reflecting an overrating capability of each of the plurality of wind turbines; and

    a power plant control (PPC) unit coupled with the PPSC unit and the optimizer unit, wherein the PPC unit is configured to;

    select, based on the plurality of overrating values, one or more wind turbines of the plurality of wind turbines for overrating; and

    communicate, based on the output power value and the plurality of overrating values, an amount of overrating to each of the selected one or more wind turbines,wherein each wind turbine of the selected one or more wind turbines processes the communicated amount of overrating through a corresponding response function to produce a respective processed overrating amount, the response function having a slope value or an offset value based on a determined fatigue amount of the wind turbine, andwherein each wind turbine changes an amount of power production by the respective processed overrating amount.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×