Energy storage system of uninterruptible power supply equipped with battery and method of driving the same
First Claim
1. An energy storage system included in an Uninterruptible Power Supply (UPS) for supplying a power source to a load that needs the uninterruptible power, comprising:
- a commercial power source unit configured to supply a first power source to the load;
a battery configured to supply a second power source to the load;
a power failure monitoring unit configured to monitor a power failure state in the commercial power source unit;
a charging/discharging determination unit configured to determine a charging state of the battery and to estimate remaining capacity of the battery;
a power source control unit configured to control the commercial power source unit and the battery in response to output of the power failure monitoring unit or the charging/discharging determination unit so that the first power source or the second power source is supplied to the load; and
an operation time setting unit configured to set a peak time zone of the load;
wherein the power source control unit, when the first power source is normal and it is the peak time zone, divides and supplies the first power source and the second power source to the load, while the second power source is supplied within an available remaining battery capacity except for an essential remaining capacity of a battery that needs to be essentially maintained in emergency;
wherein the power source control unit, when the first power source is normal and when it is not the peak time zone, controls the first power source to be supplied to the load;
wherein the power source control unit, when the first power source is cut off, controls the second power source to be supplied to the load;
wherein the power source control unit determines whether it is possible to supply only the available remaining battery capacity to the load during the peak time zone;
wherein when it is impossible to supply only the available remaining battery capacity to the load, the power source control unit calculates a current capacity that may continue to be discharged at a substantially constant rate during the peak time using only the available remaining battery capacity and supplies the calculated current capacity to the second power source during the peak time zone such that the second power source is shared with the first power source to be supplied to the load.
1 Assignment
0 Petitions
Accused Products
Abstract
Disclosed herein are the energy storage system of an Uninterruptible Power Supply (UPS) equipped with the battery and a method of driving the same. The energy storage system includes a commercial power source unit configured to supply a first power source to a load, and the battery configured to supply a second power source to the load. And the system monitors a power failure state in the commercial power source unit, determines a charging state of the battery, and controls the commercial power source unit and the battery in response to output of monitoring or determination, so that the first power source or the second power source is supplied to the load. A power reservation ratio for the use of power can be increased by reducing power used during daytime.
6 Citations
10 Claims
-
1. An energy storage system included in an Uninterruptible Power Supply (UPS) for supplying a power source to a load that needs the uninterruptible power, comprising:
-
a commercial power source unit configured to supply a first power source to the load; a battery configured to supply a second power source to the load; a power failure monitoring unit configured to monitor a power failure state in the commercial power source unit; a charging/discharging determination unit configured to determine a charging state of the battery and to estimate remaining capacity of the battery; a power source control unit configured to control the commercial power source unit and the battery in response to output of the power failure monitoring unit or the charging/discharging determination unit so that the first power source or the second power source is supplied to the load; and an operation time setting unit configured to set a peak time zone of the load; wherein the power source control unit, when the first power source is normal and it is the peak time zone, divides and supplies the first power source and the second power source to the load, while the second power source is supplied within an available remaining battery capacity except for an essential remaining capacity of a battery that needs to be essentially maintained in emergency; wherein the power source control unit, when the first power source is normal and when it is not the peak time zone, controls the first power source to be supplied to the load; wherein the power source control unit, when the first power source is cut off, controls the second power source to be supplied to the load; wherein the power source control unit determines whether it is possible to supply only the available remaining battery capacity to the load during the peak time zone; wherein when it is impossible to supply only the available remaining battery capacity to the load, the power source control unit calculates a current capacity that may continue to be discharged at a substantially constant rate during the peak time using only the available remaining battery capacity and supplies the calculated current capacity to the second power source during the peak time zone such that the second power source is shared with the first power source to be supplied to the load. - View Dependent Claims (2, 3, 4, 5)
-
-
6. A method of operating an Uninterruptible Power Supply (UPS) comprising an energy storage system for supplying a power source to a load that needs the uninterruptible power, the method comprising steps of:
-
(a) monitoring, by a power failure monitoring unit, a power failure state of a commercial power source unit for supplying a first power source to the load and determining, by a charging/discharging determination unit, a charging state of a battery for supplying a second power source to the load; (b) setting, by an operation time setting unit, a peak time zone of the load; (c) dividing, by a power source control unit, the first power source and the second power source in the peak time zone set at the step (b) and supplying the first power source and the second power source to the load when the first power source is normal; and (d) controlling, by the power source control unit, the first power source to be supplied to the load when the power source is normal and it is not the peak time zone and the second power source to be supplied to the load when the first power source is at the power failure state; wherein, in the step (c), the charging/discharging determination unit calculates a remaining capacity of a battery and the power source control unit supplies the second power source within an available remaining battery capacity except for an essential remaining capacity of the battery that needs to be essentially maintained in emergency; wherein, in the step (c), the power source control unit determines whether only the available remaining battery capacity may be supplied to the load during the peak time zone, and when it is impossible to supply only the available remaining battery capacity to the load, the power source control unit calculates a current capacity that may continue to be discharged at a substantially constant rate during the peak time using only the available remaining battery capacity and supplies the calculated current capacity to the second power source during the peak time zone such that the second power source is shared with the first power source to be supplied to the load. - View Dependent Claims (7, 8, 9, 10)
-