Charge control device, battery management device, charge control method, and record medium
First Claim
1. A charge control device that controls charging of a plurality of vehicles, which use electric power as a drive source, using electric power from an electric power grid, comprising:
- a storage unit that stores a first period in a charge control period for which the charging is controlled;
a second period other than the first period in the charge control period; and
a target level of a charge demand in the first period;
a receipt unit that receives from each of the plurality of vehicles a required charge amount;
a control unit that controls the charging using as a target the target level of the charge demand in the first period, sets up a target level of charging in the second period based on a remaining total amount that is generated by subtracting the charge amount in the first period from a total amount of the plurality of required charge amounts, and controls the charging using as a target the target level of the charging, andan assignment unit that assigns charge priorities to the plurality of vehicles based on a predetermined condition comprising a factor calculated by the formula [Required charge amount/(Remaining charge time×
Charge electric power)], wherein the assignment unit assigns a higher charge priority to a vehicle having a larger factor.
1 Assignment
0 Petitions
Accused Products
Abstract
A charge-control device that controls charging of vehicles, which use electric power as a drive source, using electric power from an electric power grid includes storage means storing a first period in a charge control period for which the charging is controlled; a second period other than the first period in the charge control period; and a target level of a charge demand in the first period; receipt means receiving from each of the vehicles the required charge amount; and control means controlling the charging using the target level of the charge demand in the first period, setting up a target level of charging in the second period based on a remaining total amount generated by subtracting the charge amount in the first period from a total amount of the plurality of required charge amounts to control the charging using the target level of the charging.
-
Citations
7 Claims
-
1. A charge control device that controls charging of a plurality of vehicles, which use electric power as a drive source, using electric power from an electric power grid, comprising:
-
a storage unit that stores a first period in a charge control period for which the charging is controlled;
a second period other than the first period in the charge control period; and
a target level of a charge demand in the first period;a receipt unit that receives from each of the plurality of vehicles a required charge amount; a control unit that controls the charging using as a target the target level of the charge demand in the first period, sets up a target level of charging in the second period based on a remaining total amount that is generated by subtracting the charge amount in the first period from a total amount of the plurality of required charge amounts, and controls the charging using as a target the target level of the charging, and an assignment unit that assigns charge priorities to the plurality of vehicles based on a predetermined condition comprising a factor calculated by the formula [Required charge amount/(Remaining charge time×
Charge electric power)], wherein the assignment unit assigns a higher charge priority to a vehicle having a larger factor. - View Dependent Claims (2, 3, 4, 5)
-
-
6. A charge control method for a charge control device that controls charging of a plurality of vehicles, which use electric power as a drive source, using electric power from an electric power grid, comprising:
-
storing into a storage unit a first period in a charge control period for which the charging is controlled;
a second period other than the first period in the charge control period; and
a target level of a charge demand in the first period;receiving from each of the plurality of vehicles a required charge amount; and controlling the charging using as a target the target level of the charge demand in the first period, setting up a target level of charging in the second period based on a remaining total amount that is generated by subtracting the charge amount in the first period from a total amount of the plurality of required charge amounts, and controlling the charging using as a target the target level of the charging assigning charge priorities to the plurality of vehicles based on a predetermined condition comprising a factor calculated by the formula [Required charge amount/(Remaining charge time×
Charge electric power)], wherein a higher charge priority is assigned to a vehicle having a larger factor.
-
-
7. A non-transitory computer readable record medium on which a program that causes a computer to execute procedures is recorded, the procedures comprising:
-
a storage procedure that stores into a storage unit a first period in a charge control period for which charging of a plurality of vehicles which use electric power as a drive source using electric power from an electric power grid is controlled;
a second period other than the first period in the charge control period; and
a target level of a charge demand in the first period;a receipt procedure that receives from each of the plurality of vehicles a required charge amount; a control procedure that controls the charging using as a target the target level of the charge demand in the first period, sets up a target level of charging in the second period based on a remaining total amount that is generated by subtracting the charge amount of the charging in the first period from a total amount of the plurality of required charge amounts, and controls the charging using as a target the target level of the charging; an assignment procedure that assigns charge priorities to the plurality of vehicles based on a predetermined condition comprising a factor calculated by the formula [Required charge amount/(Remaining charge time×
Charge electric power)], wherein the assignment procedure assigns a higher charge priority to a vehicle having a larger factor.
-
Specification