1. An apparatus comprising:
- a first generator controller configured to control a breaker for connecting a first generator to a common bus and control an external breaker for selectively connecting the common bus to an external source; and
a communication interface configured to connect the first generator controller with a second generator controller configured to send a command for the external breaker for selectively connecting the common bus to the external source.
4 Assignments
0 Petitions
Accused Products
Abstract
A generator system may include redundant control. The generator system may include any combination of redundant controllers, redundant communication paths, or other redundant control. A generator system may include an electrical bus, a first generator controller, and the second generator controller. The first generator controller may control a first generator breaker for connecting a first generator to the electrical bus and configured to control an external breaker for selectively connecting the electrical bus to an external source. The second generator controller may control a second generator breaker for connecting a second generator to the common bus and configured to control the external breaker for selectively connecting the electrical bus to the external source.
-
Citations
20 Claims
-
1. An apparatus comprising:
-
a first generator controller configured to control a breaker for connecting a first generator to a common bus and control an external breaker for selectively connecting the common bus to an external source; and a communication interface configured to connect the first generator controller with a second generator controller configured to send a command for the external breaker for selectively connecting the common bus to the external source. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A system comprising:
-
an electrical bus; a first generator controller configured to control a first generator breaker for connecting a first generator to the electrical bus and configured to control an external breaker for selectively connecting the electrical bus to an external source; and a second generator controller configured to control a second generator breaker for connecting a second generator to the common bus and configured to control the external breaker for selectively connecting the electrical bus to the external source, wherein the second generator controller is configured to receive at least one command between the first generator controller and the external breaker. - View Dependent Claims (9, 10, 11, 12, 13, 14, 15, 16, 17)
-
-
18. A method comprising:
-
detecting a breaker status for a breaker connecting a distribution bus to an external source, wherein the distribution bus electrically couples a first generator and a second generator to the external source; receiving, at first generator controller, data from a second generator controller related to operation of the second generator; and generating a command for controlling the breaker for the external source in response to the breaker status and the data related to operation of the second generator. - View Dependent Claims (19, 20)
-