Power generation system with anticipatory operation
First Claim
Patent Images
1. A method comprising:
- detecting an anticipated load increase;
changing a power source from inactive to operation in an offline mode upon detection of the anticipated load increase;
monitoring a load to identify a load increase associated with the anticipated load increase; and
changing operation of a power system from the offline mode to a power supply mode upon identification of the load increase associated with the anticipated load increase.
4 Assignments
0 Petitions
Accused Products
Abstract
Systems and methods include operating a power system in a first state, and detecting an anticipated load increase. The systems and methods further include changing operation of the power system from the first state to a second state upon detection of the anticipated load increase.
-
Citations
19 Claims
-
1. A method comprising:
-
detecting an anticipated load increase; changing a power source from inactive to operation in an offline mode upon detection of the anticipated load increase; monitoring a load to identify a load increase associated with the anticipated load increase; and changing operation of a power system from the offline mode to a power supply mode upon identification of the load increase associated with the anticipated load increase. - View Dependent Claims (2, 3, 4, 5)
-
-
6. A system comprising:
-
an input configured to receive an anticipated load increase indication; a controller in communication with the input and a power system comprising a first power source and a second power source, the controller comprising; a non-transitory computer readable storage medium storing logic for controlling a power system, the logic comprising; instructions for identifying an anticipated load increase; instructions for operating the power system in a first state prior to identification of the anticipated load increase, the first power source operating in a power supply mode and the second power source being inactive when the power system is operated in the first state; instructions for operating the power system in a second state upon identification of an anticipated load increase, the first power source operating in the power supply mode and the second power source operating in an offline mode when the power system is operated in the second state; and a processor configured to execute the logic. - View Dependent Claims (7, 8, 9, 10, 11, 12, 13, 14, 15)
-
-
16. A system comprising:
-
a power source connected with a vehicle; a load anticipation unit that detects a parameter associated with the vehicle; a controller that controls an operation of the power source; wherein the power source is inactive before an anticipated load increase is identified; wherein the controller receives the parameter and identifies an anticipated load increase based on the parameter; wherein the controller controls the power source to operate in an offline mode when the anticipated load increase is identified; wherein the controller monitors a load to identify a load increase associated with the anticipated load increase; and wherein the controller controls the power source to change from operating in an offline mode to operating in a power supply mode when the load increase associated with the anticipated load increase is identified. - View Dependent Claims (17, 18, 19)
-
Specification