Qualitative and quantitative modeling of enterprise risk management and risk registers
First Claim
1. A computer-implemented system for qualitative and quantitative modeling of risk management comprising:
- a processor;
and a enterprise risk management (ERM) risk register module comprising computer-executable instructions stored in non-volatile memory,wherein said processor and said ERM risk register module are operably connected andprovide a user interface to a user, wherein said user interface is a risk register that allows said user to organize and manage one or more risk elements;
wherein said user interface allows said user to manage and designate authorized users and risk managers;
wherein said processor and said ERM risk register module receive risk element input from said user, wherein said risk element input is comprised of said one or more risk elements entered by said user;
wherein said processor and said ERM risk register module analyze said risk element input, wherein a risk analysis is performed on each of said one or more risk elements;
wherein said processor and said ERM risk register module create risk analysis charts, wherein one or more graphs are generated based on said risk analysis of each of said one or more risk elements;
wherein said processor and said ERM risk register module analyze risk level trends of said one or more risk elements, wherein in patterns of change in risk level for said one or more risk elements can be plotted over time;
wherein said processor and said ERM risk register module forecast changes in said risk level of said one or more risk elements, wherein said risk level trends are evaluated to provide a predictive analysis of future risk level change of said one or more risk elements;
wherein said processor and said ERM risk register module recommend one or more risk mitigation programs based on said risk level trends and said predictive analysis of future risk level change, wherein each of one or more risk mitigation programs are evaluated for effectiveness;
wherein said one or more mitigation programs comprise one or more mitigation measures; and
wherein said one or more mitigation measures each have a due date;
and wherein said ERM module and said processor send an alert to said designated authorized users and risk managers when said risk level of said one or more risk elements exceeds a stipulated risk level limit based on the time remaining based on the due date to complete any risk mitigation measures.
0 Assignments
0 Petitions
Accused Products
Abstract
The present invention is applicable in the field of corporate finance, corporate capital investments, economics, math, business risk analysis, simulation, decision analysis, qualitative risk analysis, risk management, quantitative risk analysis, and business statistics, and relates to the modeling and valuation of investment decisions under uncertainty and risk within all companies, allowing these firms to properly identify, assess, quantify, value, diversify, and hedge their corporate capital investment decisions and their associated risks. Specifically, the present invention looks at starting from a comprehensive qualitative risk register and moving the analysis into the realms of quantitative risk modeling, simulation, and optimization.
-
Citations
15 Claims
-
1. A computer-implemented system for qualitative and quantitative modeling of risk management comprising:
-
a processor; and a enterprise risk management (ERM) risk register module comprising computer-executable instructions stored in non-volatile memory, wherein said processor and said ERM risk register module are operably connected and provide a user interface to a user, wherein said user interface is a risk register that allows said user to organize and manage one or more risk elements; wherein said user interface allows said user to manage and designate authorized users and risk managers; wherein said processor and said ERM risk register module receive risk element input from said user, wherein said risk element input is comprised of said one or more risk elements entered by said user; wherein said processor and said ERM risk register module analyze said risk element input, wherein a risk analysis is performed on each of said one or more risk elements; wherein said processor and said ERM risk register module create risk analysis charts, wherein one or more graphs are generated based on said risk analysis of each of said one or more risk elements; wherein said processor and said ERM risk register module analyze risk level trends of said one or more risk elements, wherein in patterns of change in risk level for said one or more risk elements can be plotted over time; wherein said processor and said ERM risk register module forecast changes in said risk level of said one or more risk elements, wherein said risk level trends are evaluated to provide a predictive analysis of future risk level change of said one or more risk elements; wherein said processor and said ERM risk register module recommend one or more risk mitigation programs based on said risk level trends and said predictive analysis of future risk level change, wherein each of one or more risk mitigation programs are evaluated for effectiveness; wherein said one or more mitigation programs comprise one or more mitigation measures; and wherein said one or more mitigation measures each have a due date; and wherein said ERM module and said processor send an alert to said designated authorized users and risk managers when said risk level of said one or more risk elements exceeds a stipulated risk level limit based on the time remaining based on the due date to complete any risk mitigation measures. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
-
10. A computer-implemented method for qualitative and quantitative modeling of risk management said method comprising the steps of:
-
providing a user interface to a user, wherein said user interface is a risk register that allows said user to organize and manage one or more risk elements; allowing said user to manage and designate authorized users and risk managers; receiving risk element input from said user, wherein said risk element input is comprised of said one or more risk elements entered by said user; analyzing said risk element input, wherein a risk analysis is performed on each of said one or more risk elements; creating risk analysis charts, wherein one or more graphs are generated based on said risk analysis of each of said one or more risk elements; analyzing risk level trends of said one or more risk elements, wherein in patterns of change in risk level for said one or more risk elements can be plotted over time; forecasting changes in said risk level of said one or more risk elements, wherein said risk level trends are evaluated to provide a predictive analysis of future risk level change of said one or more risk elements; and recommending one or more risk mitigation programs based on said risk level trends and said predictive analysis of future risk level change, wherein each of one or more risk mitigation programs are evaluated for effectiveness; wherein said one or more mitigation programs comprise one or more mitigation measures; and
wherein said one or more mitigation measures each have a due date;sending an alert to said designated authorized users and risk managers when said risk level of said one or more risk elements exceeds a stipulated risk level limit based on the time remaining based on the due date to complete any risk mitigation measures. - View Dependent Claims (11, 12, 13, 14, 15)
-
Specification