Management system and management method for mining machine

  • US 10,089,863 B2
  • Filed: 08/30/2013
  • Issued: 10/02/2018
  • Est. Priority Date: 08/30/2013
  • Status: Active Grant
First Claim
Patent Images

1. A management system of a mining machine comprising:

  • a position information detector which is mounted on a mining machine enabled to travel on a route in a mine and detects position information about the mining machine;

    an operation information detector which is mounted on the mining machine and detects operation information about the mining machine; and

    a first evaluation device which evaluates the operation information based on the position information and the operation information,wherein the route in the mine includes a plurality of nodes disposed at a predetermined distance and a plurality of links connecting between the nodes adjacent to each other, and includes route information including a specific section in which a difference in a gradient between the links adjacent to each other is a predetermined value or less, a difference in an orientation between the links adjacent to each other is a predetermined value or less, and no intersection exists between the links adjacent to each other,wherein the first evaluation device evaluates the operation information in the specific section of the route,wherein the route includes a plurality of specific sections,wherein the management system comprises a second evaluation device which evaluates an index of production efficiency of the mining machine including an amount of fuel consumed per unit time and a transport load per unit time of the mining machine in each of the plurality of specific sections,wherein the second evaluation device generates two reference axes of a two-dimensional graph which indicate the amount of fuel consumed per unit time and the transport load per unit time of the index respectively and a mean value of the indexes of the plurality of specific sections,wherein the management system further comprises a second output device which outputs the index in association with each of the plurality of specific sections,wherein the second output device outputs the index as the two-dimensional graph in which one of the two axes is a vertical axis, the other is a horizontal axis, and the mean value of the indexes of the plurality of specific sections is an origin point,wherein the second output device outputs a line indicating the transport load per unit amount of fuel consumed to be an evaluation reference and a point indicating the index of each of the plurality of specific sections to the two-dimensional graph, andwherein operation of the mining machine is managed in light of the information from the two-dimensional graph to improve production efficiency of the mining machine including an amount of fuel consumed per unit time and a transport load per unit time of the mining machine.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×