Management of materials on a construction site

  • US 10,133,994 B2
  • Filed: 09/25/2012
  • Issued: 11/20/2018
  • Est. Priority Date: 12/01/2008
  • Status: Active Grant
First Claim
Patent Images

1. A method for management of a cut and fill operation on a construction site, said method comprising:

  • receiving, by a computer, a digital model of the construction site, the digital model identifying cut regions of the construction site where a material is to be removed and fill regions of the construction site where the material is to be deposited;

    receiving, by the computer, information about each vehicle in a vehicle pool comprising a plurality of vehicles, the received information including type of each vehicle, load capacity of each vehicle, and operating costs of each vehicle, wherein the vehicle pool includes different types of vehicles having different load capacities and different operating costs;

    generating, by the computer, a cost scenario that defines cost over distance for each vehicle in each vehicle pool based at least on the load capacity of each vehicle, the operating cost of each vehicle, type of the material, and moisture content of the material;

    receiving, by the computer, site conditions including type of roads between the cut regions and the fill regions of the construction site and geological information about the cut regions;

    generating, by the computer, a report based on the digital model, the cost scenario, and the site conditions that includes a machine work flow plan for each vehicle in the vehicle pool, each machine work flow plan identifying loads of the material that are to be moved by a respective vehicle and a travel route between said cut region and said fill region for each load;

    transmitting, from the computer, a respective machine work flow plan to each vehicle in the vehicle pool;

    receiving, by the computer and from each vehicle, an actual drop-off location of each load of said material moved by said respective vehicle and machine control information for said respective vehicle, wherein each vehicle is equipped with a Global Navigation Satellite System (GNSS) system and a machine control system;

    calculating, by the computer, differences between actual movement of said material and planned movement of said material for each vehicle;

    generating, by the computer, a new machine work flow plan for each vehicle that accounts for the difference between said actual movement of said material and said planned movement of said material for each vehicle;

    transmitting, from the computer, a new respective machine work flow plan to each vehicle such that the new respective machine work flow plan replaces the respective machine work flow plan for each vehicle;

    and implementing, by at least one vehicle, the new respective machine work flow plan, thereby modifying operations of the at least one vehicle based on the new respective machine work flow plan.