Redundant flexible datacenter workload scheduling
First Claim
1. A system comprising:
- a first flexible datacenter comprising;
a first behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid,a first power distribution system,a first datacenter control system, anda first plurality of computing systems powered by the first behind-the-meter power input system via the first power distribution system, wherein the first datacenter control system is configured to modulate power delivery to the first plurality of computing systems based on one or more monitored power system conditions or an operational directive;
a second flexible datacenter comprising;
a second behind-the-meter power input system,a second power distribution system,a second datacenter control system, anda second plurality of computing systems powered by the second behind-the-meter power input system via the second power distribution system, wherein the second datacenter control system is configured to modulate power delivery to the second plurality of computing systems based on one or more monitored power system conditions or an operational directive; and
a routing control system configured to (i) identify a computational operation to be performed, (ii) determine whether to route at least a portion of the computational operation to the first flexible datacenter, and (iii) based on a determination to route at least the portion of the computational operation to the first flexible datacenter, cause a first portion of the computational operation to be sent to the first flexible datacenter and a second portion of the computational operation to be sent to the second flexible datacenter.
1 Assignment
0 Petitions
Accused Products
Abstract
Systems include one or more critical datacenter connected to behind-the-meter flexible datacenters. The critical datacenter is powered by grid power and not necessarily collocated with the flexible datacenters, which are powered “behind the meter.” When a computational operation to be performed at the critical datacenter is identified and determined that it can be performed more efficiently or advantageously at a flexible datacenter, the computational operation is instead obtained by the flexible datacenters for performance. The critical datacenter and flexible datacenters preferably share a dedicated communication pathway to enable high-bandwidth, low-latency, secure data transmissions. In some situations, a computational operation is supported by multiple datacenters in a redundant arrangement, such as multiple flexible datacenters.
78 Citations
17 Claims
-
1. A system comprising:
-
a first flexible datacenter comprising; a first behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid, a first power distribution system, a first datacenter control system, and a first plurality of computing systems powered by the first behind-the-meter power input system via the first power distribution system, wherein the first datacenter control system is configured to modulate power delivery to the first plurality of computing systems based on one or more monitored power system conditions or an operational directive; a second flexible datacenter comprising; a second behind-the-meter power input system, a second power distribution system, a second datacenter control system, and a second plurality of computing systems powered by the second behind-the-meter power input system via the second power distribution system, wherein the second datacenter control system is configured to modulate power delivery to the second plurality of computing systems based on one or more monitored power system conditions or an operational directive; and a routing control system configured to (i) identify a computational operation to be performed, (ii) determine whether to route at least a portion of the computational operation to the first flexible datacenter, and (iii) based on a determination to route at least the portion of the computational operation to the first flexible datacenter, cause a first portion of the computational operation to be sent to the first flexible datacenter and a second portion of the computational operation to be sent to the second flexible datacenter. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10)
-
-
11. A system comprising
a plurality of flexible datacenters, each flexible datacenter comprising: -
a behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid, a power distribution system, a datacenter control system, and a plurality of computing systems powered by the behind-the-meter power input system, wherein the datacenter control system is configured to modulate power delivery to the plurality of computing systems based on one or more monitored power system conditions or an operational directive; and a routing control system configured to (i) identify a computational operation to be performed, (ii) determine whether to route the computational operation to at least two flexible datacenters in the plurality of flexible datacenters, (iii) based on a determination to route the computational operation to at least two flexible datacenters in the plurality of flexible datacenters, determine a first flexible datacenter in the plurality of flexible datacenters to route a first portion of the computational operation to and a second flexible datacenter in the plurality of flexible datacenters to route a second portion of the computational operation to, and (iv) cause the first portion of the computational operation to be sent to the first flexible datacenter and the second portion of the computational operation to be sent to the second flexible datacenter with instructions that specify for the first flexible datacenter to complete the first portion of the computational operation prior to the second flexible datacenter initiating computation of the second portion of the computational operation. - View Dependent Claims (12, 13, 14, 15, 16, 17)
-
Specification