Photovoltaic energy storage air conditioner and control method thereof

  • US 10,784,711 B2
  • Filed: 01/23/2017
  • Issued: 09/22/2020
  • Est. Priority Date: 02/03/2016
  • Status: Active Grant
First Claim
Patent Images

1. A photovoltaic energy storage air conditioner, comprising a photovoltaic power generation device, an energy storage device, an air conditioning unit and an energy scheduling and management device;

  • wherein the photovoltaic power generation device, the energy storage device and a public power grid are connected to the air conditioning unit for power supply;

    the photovoltaic power generation device and the public power grid are connected to the energy storage device for charging;

    the photovoltaic power generation device is configured to comply a grid-connected power supply to the public power grid; and

    wherein the energy scheduling and management device comprises;

    a detection module, configured to detect an operation state of the air conditioner, a power supply quantity and a working state of the photovoltaic power generation device and a power supply quantity and a working state of the energy storage device;

    a scheduling module, configured to control power supply and/or charging according to the operation state of the air conditioner, the power supply quantity and the working state of the photovoltaic power generation device, the power supply quantity and the working state of the energy storage device, preset power supply priorities and power usage priorities; and

    wherein;

    (i) the scheduling module is adapted to control the photovoltaic power generation device only to be a power supply for supplying power to the air conditioning unit, when determining that power generated by the photovoltaic power generation device is the same as power required for operation of the air conditioning unit;

    the scheduling module is adapted to control the photovoltaic power generation device to charge the energy storage device, when determining that the air conditioning unit is not operating and power of the energy storage device is insufficient to operate the air conditioner; and

    the scheduling module is adapted to control the photovoltaic power generation device to comply the grid-connected power supply to the public power grid, when determining that the air conditioning unit is not operating and the energy storage device has sufficient power to operate the air conditioner or is not working;

    or(ii) the scheduling module is adapted to control the energy storage device to drive the air conditioning unit to operate when determining that the photovoltaic power generation device is not generating power and power of the energy storage device is sufficient to operate the air conditioner;

    the scheduling module is adapted to control the public power grid to charge the energy storage device when determining that the photovoltaic power generation device is not generating power and the air conditioning unit is not operating and power of the energy storage device is insufficient to operate the air conditioner;

    the scheduling module is adapted to control the public power grid to drive the air conditioning unit to operate and control the public power grid to charge the energy storage device when determining that the photovoltaic power generation device is not generating power and power of the energy storage device is insufficient to operate the air conditioner; and

    the scheduling module is adapted to control the photovoltaic power generation device to supply power to the air conditioning unit and control the photovoltaic power generation device to charge the energy storage device, when determining that power generated by the photovoltaic power generation device is more than power required for the operation of the air conditioning unit, and power of the energy storage device is insufficient to operate the air conditioner;

    or(iii) the scheduling module is adapted to control the photovoltaic power generation device to supply power to the air conditioning unit and control the photovoltaic power generation device to comply the grid-connected power supply to the public power grid, when determining that power generated by the photovoltaic power generation device is more than power required for the operation of the air conditioning unit, and the energy storage device has sufficient power to operate the air conditioner or is not working;

    the scheduling module is adapted to control the photovoltaic power generation device and the public power grid to supply power to the air conditioning unit jointly and control the public power grid to charge the energy storage device, when determining that power generated by the photovoltaic power generation device is less than power required for the operation of the air conditioning unit, and power of the energy storage device is insufficient to operate the air conditioner; and

    the scheduling module is adapted to control the photovoltaic power generation device and the energy storage device to supply power to the air conditioning unit jointly, when determining that power generated by the photovoltaic power generation device is less than power required for the operation of the air conditioning unit and power of the energy storage device is sufficient to operate the air conditioner.