×

Offshore floating production method

  • US 20020157833A1
  • Filed: 04/04/2002
  • Published: 10/31/2002
  • Est. Priority Date: 04/25/2001
  • Status: Active Grant
First Claim
Patent Images

1. A method of conducting operations to an offshore field from multiple separated drill centers, the method using a floating vessel having a turret-mounted mooring element positioned at or near one end of the vessel which allows the vessel to weathervane and further having a workstation horizontally spaced apart from the mooring element, comprising the steps of:

  • (a) locating the mooring element approximately over a first mooring element location;

    (b) limiting the horizontal movement of the mooring element using a plurality of mooring lines extending from the mooring element;

    (c) allowing the vessel to weathervane such that the workstation is substantially vertically aligned over a first drill center associated with the first mooring element location, (d) temporarily restraining the weather-vaning of the vessel;

    (e) using the workstation to conduct operations in at least one well from the first drill center to the field;

    (f) removing the weather-vaning restraint while continuing to limit horizontal movement of the moving element and repeating steps (c), (d) and (e) for one or more additional drill centers associated with the first mooring element location.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×