1. A suspended scaffolding bracket for a building under construction, comprising:
- a horizontal support having a first end and a second end;
a vertical support having a top end and a bottom end, wherein the bottom end is attached to the first end of the horizontal support; and
an anchor assembly structured to make contact with inside and top surfaces of a crossbeam of the building such that construction work adjacent the crossbeam can be completed without removing the scaffolding bracket.
1 Assignment
0 Petitions
Accused Products
Abstract
A suspended scaffolding system and method of use employs a plurality of scaffolding brackets that are hung from the framework of a building under construction to support a plurality of scaffolding planks to form a walkway therebetween. The scaffolding brackets include an anchor assembly, which is specially designed to wrap around the building'"'"'s framework such that construction workers can complete their work without removing the brackets.
4 Citations
51 Claims
-
1. A suspended scaffolding bracket for a building under construction, comprising:
-
a horizontal support having a first end and a second end;
a vertical support having a top end and a bottom end, wherein the bottom end is attached to the first end of the horizontal support; and
an anchor assembly structured to make contact with inside and top surfaces of a crossbeam of the building such that construction work adjacent the crossbeam can be completed without removing the scaffolding bracket. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18)
-
-
19. A suspended scaffolding system for a building under construction, comprising:
-
a plurality of scaffolding brackets, each bracket comprising;
a horizontal support having a first end and a second end;
a vertical support having a top end and a bottom end, wherein the bottom end is attached to the first end of the horizontal support; and
an anchor assembly structured to make contact with inside and top surfaces of a crossbeam of the building such that construction work adjacent the crossbeam can be completed without removing the scaffolding brackets; and
a plurality of scaffolding planks spanning the plurality of scaffolding brackets and forming a walkway. - View Dependent Claims (20, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36)
-
-
21. The suspended scaffolding system 20, wherein each horizontal plate is structured make contact with only a portion of the top surface of a crossbeam.
-
37. A method of installing a suspended scaffolding system around a building under construction, comprising the steps of:
-
providing a plurality of scaffolding brackets, each scaffolding bracket including a horizontal support, a vertical support and an anchor assembly located at a top end of the vertical support;
wherein the anchor assembly is structured to make contact with a crossbeam of the building under construction; and
maneuvering each scaffolding bracket such that each anchor assembly makes contact with upper and inner surfaces of a crossbeam of the building under construction. - View Dependent Claims (38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51)
-