Web-based risk management tool and method
First Claim
1. A method of managing risk related to a successful completion of a development project, comprising:
- storing a probability of occurrence (Pf) table and a severity of consequence (Cf) table, identified risks and existing risk mitigation plans in a shared risk database; and
via a web browser, a plurality of users, formulating an enterprise search of the risk database to identify at least one risk, viewing the Pf table to select a probability of occurrence Pf for said at least one risk;
viewing the Cf table to select a severity of consequence Cf for said at least one risk, said Pf and Cf being combined and ranked to define prioritized risk factors Rf, formulating a mitigation search of the risk database to identify existing risk mitigation plans for the identified risk to enhance the development of new mitigation plans or share with other programs the resources to implement the mitigation plan.
1 Assignment
0 Petitions
Accused Products
Abstract
The present invention provides a risk management tool and method for creating an improved initial risk management process that captures, assesses, and prioritizes risks and implements mitigation plans to more effectively manage risk in large-scale development projects. A web-based system allows users and management to share and access risk information to more readily identify and assess risks, develop mitigation plans and track the risk management process. The tool and specifically the Pf and Cf tables are tailored to each project to more accurately calculate and prioritize risk factors RF and thus anticipate and minimize or eliminate risks before they occur. The demonstrated value of the tool is found in timely deliveries and a reduction of cost overruns as well as an increase in customer enhanced award fees.
95 Citations
28 Claims
-
1. A method of managing risk related to a successful completion of a development project, comprising:
-
storing a probability of occurrence (Pf) table and a severity of consequence (Cf) table, identified risks and existing risk mitigation plans in a shared risk database; and
via a web browser, a plurality of users, formulating an enterprise search of the risk database to identify at least one risk, viewing the Pf table to select a probability of occurrence Pf for said at least one risk;
viewing the Cf table to select a severity of consequence Cf for said at least one risk, said Pf and Cf being combined and ranked to define prioritized risk factors Rf, formulating a mitigation search of the risk database to identify existing risk mitigation plans for the identified risk to enhance the development of new mitigation plans or share with other programs the resources to implement the mitigation plan. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14)
-
-
15. A method of managing risk related to a successful completion of a development project, comprising:
-
tailoring a probability of occurrence (Pf) table having a number of risk categories to have a fewer number of said risk categories that are relevant to the development project, each said category having table entries that include standardized qualitative probability definitions;
tailoring a severity of consequence (Cf) table having a schedule impact category with table entries specifying an amount in days, weeks or months and having a cost impact category with table entries specifying multiple sub-categories of cost impacts in actual dollars for the development project;
identifying a plurality of risks relating to the successful completion of the development project;
assigning a risk factor (Rf) to each risk by selecting the table entry Pf for the risk category in the Pf table that most closely describes the risk, selecting the table entries Cf for the cost impact and schedule impact categories in the Cf table, computing a function of Pf and Cf. and keeping the highest risk factor Rf, and prioritizing the risks based on the assigned risk factors Rf. - View Dependent Claims (16, 17, 18)
-
-
19. A web-based risk management system for managing risk related to a successful completion of a development project, comprising:
-
a server comprising a shared risk database that stores a probability of occurrence (Pf) table and a severity of consequence (Cf) table, risk identification information and risk mitigation information;
a web-based risk management tool on the server that provides standardized interfaces for searching, viewing and entering information to and from the shared risk data base via a web browser;
an intranet; and
a plurality of computer workstations in communication with the server via the intranet, each said workstation provided with a web browser to search the database using the standardized interfaces to identify risks, to select entries from the Pf and Cf tables to calculate and prioritize a risk factor Rf for each risk, and to search the database to identify existing risk mitigation plans for the prioritized risks. - View Dependent Claims (20, 21, 22, 23, 24)
-
-
25. A web-based risk management system for managing risk related to a successful completion of a development project, comprising:
-
a server comprising a shared risk database that stores a probability of occurrence (Pf) table having a number of risk categories and a severity of consequence (Cf) table having a schedule impact category with table entries specifying an amount in days, weeks or months and having a cost impact category with table entries specifying multiple sub-categories of cost impacts in actual dollars for the development project, risk identification information and risk mitigation information;
a web-based risk management tool on the server that provides standardized interfaces having a menu bar with menu items and menu sub-items for searching, viewing and entering information to and from the shared risk data and hyperlinks to the Pf and Cf tables base via a web browser;
an intranet;
a computer workstation in communication with the server via the intranet, said workstation provided with a web browser for tailoring the Pf table to have a fewer number of said risk categories and the Cf table to specify the dollar amounts for the cost impact sub-categories and the days, weeks or months for the schedule impact;
a plurality of computer workstations in communication with the server via the intranet, each said workstation provided with a web browser to search the database to identify risks, to select entries from the tailored Pf and Cf tables to calculate and prioritize a risk factor Rf for each risk, to search the database to identify risk mitigation information for the prioritized risks and to track and report on the status of identified risks. - View Dependent Claims (26, 27, 28)
-