Method and apparatus for scheduling work orders in a manufacturing process
First Claim
1. A computerized method for scheduling a plurality of work orders for manufacturing products in a manufacturing process, each work order comprising a set of operations to be performed using a plurality of resources and materials, the method comprising:
- (1) receiving data in a computer, said data comprising;
(a) resource availability information for each resource used in the manufacturing process;
(b) material availability information for each material used in the manufacturing process;
(c) work order information comprising, for each work order to be scheduled;
(i) a release date for the work order and a want date for the work order;
(ii) operations information comprising the identity and sequence of operations to be performed for the work order, the identity of the resources needed to perform each operation, a minimum resource capacity needed to perform each operation, and the time needed to perform each operation; and
(iii) material requirements information comprising the identity of the materials needed to perform each operation and the quantity of each material needed for the operation;
(2) assigning resource capacity and a start date/time and a finish date/time to each operation based upon the resource availability information, the material availability information, and the work order information; and
(3) displaying on a computer screen the assigned resource capacity, the assigned start date/time, and the assigned finish date/time for each operation in a graphical format.
14 Assignments
0 Petitions
Accused Products
Abstract
A computerized system is provided for scheduling a plurality of work orders in a manufacturing process. Each work order to be scheduled specifies a set of operations to be performed using a plurality of resources and materials. Data including resource availability information for each resource used in the manufacturing process, material availability information for each material used in the manufacturing process, and work order information is received and stored in a computer. The work order information includes a release date for the work order, a want date for the work order, operations information, and material requirements information. The operations information includes the identity and sequence of operations to be performed for the work order, the identity of the resources needed to perform each operation, a minimum resource capacity needed to perform each operation, and the time needed to perform the operation. The materials information includes the identity of the materials needed to perform each operation and the quantity of each material needed for the operation. Resource capacity and a start date/time and a finish date/time are assigned to each operation based upon the resource availability information, the material availability information, and the work order information. The assigned resource-capacity, the assigned start date/time, and the assigned finish date/time for each operation are displayed on a computer screen in a graphical format.
24 Citations
44 Claims
-
1. A computerized method for scheduling a plurality of work orders for manufacturing products in a manufacturing process, each work order comprising a set of operations to be performed using a plurality of resources and materials, the method comprising:
-
(1) receiving data in a computer, said data comprising;
(a) resource availability information for each resource used in the manufacturing process;
(b) material availability information for each material used in the manufacturing process;
(c) work order information comprising, for each work order to be scheduled;
(i) a release date for the work order and a want date for the work order;
(ii) operations information comprising the identity and sequence of operations to be performed for the work order, the identity of the resources needed to perform each operation, a minimum resource capacity needed to perform each operation, and the time needed to perform each operation; and
(iii) material requirements information comprising the identity of the materials needed to perform each operation and the quantity of each material needed for the operation;
(2) assigning resource capacity and a start date/time and a finish date/time to each operation based upon the resource availability information, the material availability information, and the work order information; and
(3) displaying on a computer screen the assigned resource capacity, the assigned start date/time, and the assigned finish date/time for each operation in a graphical format. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23)
-
-
24. A computerized system for scheduling a plurality of work orders for manufacturing products in a manufacturing process, each work order comprising a set of operations to be performed using a plurality of resources and materials, the system comprising:
-
(1) means for receiving data in a computer, said data comprising;
(a) a resource availability information for each resource used in the manufacturing process;
(b) material availability information for each material used in the manufacturing process;
(c) work order information comprising, for each work order to be scheduled;
(i) a release date for the work order and a want date for the work order;
(ii) operations information comprising the identity and sequence of operations to be performed for the work order, the identity of the resources needed to perform each operation, a minimum resource capacity needed to perform each operation, and the time needed to perform each operation; and
(iii) material requirements information comprising the identity of the materials needed to perform each operation and the quantity of each material needed for the operation;
(2) means for assigning resource capacity and a start date/time and a start date/time to each operation based upon the resource availability information, the material availability information, and the work order information; and
(3) means for displaying on a computer screen the assigned resource capacity, the assigned start date/time, and the assigned finish date/time for each operation in a graphical format. - View Dependent Claims (25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42)
-
-
43. The system according to claim 43, wherein said displaying means comprises means for displaying a variable range of dates on the computer screen.
-
44. A method for scheduling a plurality of operations in a manufacturing process, each operation to be performed using a plurality of resources and materials, the method comprising:
-
(1) receiving and storing data in a computer, said data comprising;
(a) resource information comprising the identity of the resources needed to perform each operation, a minimum resource capacity needed to perform each operation, and the availability of each of said resources;
(b) materials information comprising the identity of the materials needed to perform each operation, the quantity of each material needed to perform each operation, and the availability of each of said materials;
(2) assigning resource capacity, a start date/time, and a finish date/time to the operation based upon the resource information and the materials information;
arid(3) displaying on a computer screen the assigned resource capacity, the assigned start date/time, and the assigned finish date/time for each operation in a graphical format.
-
Specification