Consolidation of member schedules with a project schedule in a network-based project schedule management system
First Claim
1. A computer-implemented method for managing a project schedule using a database, the method comprising:
- storing in a project task database table, via a project schedule editor session, planned schedule dates for project tasks;
storing in a first-level member task database table from a set of hierarchically-related member task database tables, via a member schedule editor session being used by a particular project member, planned schedule dates for a subtask of a project task, wherein the subtask is assigned to the particular project member;
storing in the first-level member task database table, via a member schedule editor session being used by the particular project member, planned schedule dates for a non-project task associated with the particular project member;
wherein the project task database table is linked to planned schedule dates contained in the first-level member task database table and wherein each member task database table other than the lowest level member task database table is linked to planned schedule dates contained in a respective next-lower-level member task database table;
retrieving from the first-level member task database table and displaying in a member schedule web page, planned schedule dates for the subtask and for the non-project task; and
displaying a project schedule for the project in a project schedule web page without displaying the non-project task.
1 Assignment
0 Petitions
Accused Products
Abstract
A system is used for the creation, maintenance, and management of an overall project schedule, of individual project member schedules, and of project task assignments over a network. The system comprises three editors accessed through a web browser to perform the various tasks by members of a project. Information is passed between a web server and web browser and a database is used to maintain all information. The project manager can use a task assignment editor to assign tasks to individual project members. The project manager can use a project schedule editor to initially create the project schedule and to show the overall project schedule. After the project schedule is created, each project member can create their own member schedule using a member schedule editor, containing tasks related to the project schedule. After project members complete a task, the project member updates the member'"'"'s schedule via the member schedule editor.
122 Citations
16 Claims
-
1. A computer-implemented method for managing a project schedule using a database, the method comprising:
-
storing in a project task database table, via a project schedule editor session, planned schedule dates for project tasks; storing in a first-level member task database table from a set of hierarchically-related member task database tables, via a member schedule editor session being used by a particular project member, planned schedule dates for a subtask of a project task, wherein the subtask is assigned to the particular project member; storing in the first-level member task database table, via a member schedule editor session being used by the particular project member, planned schedule dates for a non-project task associated with the particular project member; wherein the project task database table is linked to planned schedule dates contained in the first-level member task database table and wherein each member task database table other than the lowest level member task database table is linked to planned schedule dates contained in a respective next-lower-level member task database table; retrieving from the first-level member task database table and displaying in a member schedule web page, planned schedule dates for the subtask and for the non-project task; and displaying a project schedule for the project in a project schedule web page without displaying the non-project task. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16)
-
Specification