1. A method, comprising:

  • establishing a reference performance model for a reference photovoltaic (PV) system at a reference site;

    establishing a performance factor for an installed PV system based on configuration parameters of the installed PV system, measurements of the installed PV system, weather data at an installation site of the installed PV system and a comparison of the measurements of the installed PV system to the reference performance model; and

    predicting production of the installed PV system based on the performance factor, cumulative weather data and a time dependent performance ratio.